Plan for temporary driveway closures on SR 289 (Ruby Road) beginning April 8

Learn more

Lane restrictions to continue weekdays through April

The Arizona Department of Transportation advises that temporary partial driveway closures on State Route 289 are scheduled to begin Wednesday, April 8, as work continues on a pavement rehabilitation project.

Driveways will be closed for 15 minutes to allow placement, compacting and curing of asphalt.

Drivers should also plan for daytime lane restrictions on SR 289 (Ruby Road) near Peña Blanca Lake from 5 a.m. to 6:30 p.m. weekdays through April. The following lane restrictions are scheduled:

  • Daytime lane restrictions on east- and westbound SR 289 (Ruby Road) between mileposts 1 and 9
  • Flagging operation in the project area
  • A 14-foot vehicle width restriction
  • 25 mph speed limit in the work zone

Drivers should allow extra travel time, use caution, be prepared to slow down and merge safely when approaching and traveling through all work zones.

Schedules are subject to change due to weather and other unforeseen circumstances.

Show less

SR 289, I-19 to Peña Blanca Lake Pavement Rehabilitation

SR 289, I-19 to Peña Blanca Lake Pavement Rehabilitation

Contents

Overview

The Arizona Department of Transportation is working on a pavement rehabilitation project, on State Route 289 from milepost 0 (Ruby Road) to milepost 11 (Peña Blanca Lake parking lot) approximately seven miles north of the city of Nogales. Construction began in October 2025.

Key Elements of The Project Include:

  • Milling and repaving of the roadway surface
  • Replacing pavement markings
  • Replacing guardrail 
  • Replacing pipe culverts and install scour protection
  • Removing and replacing existing loop detectors
  • Replacing bridge deck seals at I-19 overpass
  • Install new fencing 
  • And other miscellaneous improvements 

Project Area Map

Project Area Map SR 289, I-19 to Peña Blanca Lake Pavement Rehabilitation

What to Expect

  • Flaggers and temporary portable traffic devices will direct traffic through the project area during construction. 
  • One lane of travel will be maintained during construction.
  • Construction is tentatively scheduled from 6 a.m. to 6 p.m. Monday through Friday. 
  • ADOT will provide advance notice of restrictions and closures to email subscribers and on the project website.

Project Photos

SR 289 Pre rehab pavement I-19 to Pena Blanca Lake

Video Gallery

SR 289: Pena Blanca Lake to I-19

SR 289: Pre Rehabilitation

SR 289: Pavement Restoration

Schedule

Construction began in October 2025 and is expected to be completed in the spring of 2026. Schedules are subject to change due to weather and other unforeseen situations.

Stay Informed

...

By email: Subscribe to receive project updates and traffic alerts.
By phone: Call the ADOT Project Information Line at 855.712.8530.
Online: Submit a question or comment via email to Dulce Maria Rojo at [email protected]

For real-time highway conditions statewide, follow ADOT on Twitter  (@ArizonaDOT), visit az511.gov or call 511, except while driving.