State Route 64 improvement project north of Williams starting

Learn more

Restrictions will be in place at times, overnight paving work is planned

A project to resurface and make other improvements along a 19-mile stretch of State Route 64 in the Williams area is scheduled to ramp up the week of April 6. Some initial work, including the placement of portable message signs, has started this week (March 30-April 3). 

Resurfacing along SR 64 will take place between the Interstate 40 interchange and Pipeline Road. Crews also are scheduled to add left turn lanes at several intersections, including Pronghorn Ranch and Sunset Strips roads. 

Drivers should plan for intermittent daytime lane restrictions along SR 64 Mondays through Thursdays and Friday mornings. 

Paving improvements will include upgrades at more than 50 driveways and pullouts. The resurfacing work is scheduled to take place mostly during overnight hours, typically from 7 p.m. to 7 a.m. Sunday through Thursday nights. 

The $19.4 million project is scheduled for completion by fall 2027.

Show less

SR 64: I-40 to Pipeline Road Pavement Preservation

SR 64: I-40 to Pipeline Road Pavement Preservation

Contents

Project cost: $33,000,000

Overview 

The Arizona Department of Transportation has initiated a pavement preservation project along State Route 64 between I-40 in Williams and Pipeline Road (mileposts 185-205). 

Project Elements

  • Remove and replace the top layer of pavement in designated areas 
  • Construct turn lanes
  • Pave and/or rehabilitate pavement on turnouts 
  • Build up shoulders  
  • Conduct bridge work
  • Improve culverts
  • Remove and install new guardrail
  • Remove and replace roadway striping and rumble strips 
  • Remove and replace new fencing
  • Install traffic loop detectors
  • Trim and/or remove vegetation, as needed 
  • Reseed disturbed areas with native plant species, as needed
  • Remove and replace cattle guard
  • Erosion control, as needed

Project Flyer

Project Area Map

Map showing a project area highlighted in orange along Route 64 between mileposts MP185 near Interstate 40 by Williams and MP205 near Pipeline Road, with Flagstaff indicated to the east. A legend marks the project area and mileposts, and the map notes it is not to scale.

Project Schedule

Construction is scheduled to begin spring 2026 with final completion anticipated for fall 2027. 

What to expect:

Intermittent daytime lane restrictions will be in place from 6 a.m. to 6 p.m., Mondays through Thursdays. Paving work will take place overnight from 7 p.m. to 7 a.m., Sunday evenings through Friday mornings. 

When needed, flaggers and a pilot car will guide drivers through the work zone. 

ADOT advises drivers to plan for delays while the work is underway.

Restrictions and Closures

Stay informed of traffic restrictions before they occur by subscribing to receive notifications sent directly to your email. It’s fast and easy! All we need is your email address.

For real-time information about project-related restrictions and closures, visit az511.gov or call 511, except while driving.

Remember to slow down and use caution around construction workers and equipment.

Stay Informed:

...

Subscribe to receive traffic alerts and project updates directly to your email.

  • Email/Phone: Community Relations Project Manager Jason Stephens at [email protected] or 480.751.7104.
  • Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530.
  • Mail: Jason Stephens, ADOT Communications, 1655 W. Jackson St., MD 126F, Phoenix, AZ 85007.