I-40 Bridges (Painted Desert, Navajo, Chambers, Querino)

   

The Arizona Department of Transportation is reconstructing four bridges on I-40 east of Holbrook. The cost of this project is $2,999,998. The bridges are located at the Painted Desert Traffic Interchange milepost 311, the Navajo Traffic Interchange milepost 325, The Chambers Traffic Interchange milepost 333 and the Querino Traffic Interchange milepost 343. During the construction of each bridge, traffic will not be able to cross the interstate to access the opposite side. Traffic wishing to access the opposite side will need to use the next closest interchange on the east or west side of each bridge. The entire project is scheduled to be completed by late fall 2013, but certain bridges may be completed before that time.

ADOT will make every effort to minimize impacts on the traveling public during construction.

While ADOT strives to inform the public about planned roadway restrictions during any construction project, there is a possibility that unscheduled closures or restrictions may occur due to weather and other unforeseen circumstances.

Map

Painted Desert Traffic Interchange (I-40 Milepost 311)

Work on the Painted Desert Interchange will consist of replacing the superstructure and bridge deck. Work will start September 3 and end October 28 2013. The Painted Desert Traffic Interchange is the only access off of I-40 into the Petrified Forest National Park. Motorists traveling east on I-40 may access the park by taking US 180 out of Holbrook to the south entrance or they may proceed past the north entrance on I-40 to the next interchange Pinta Road, (milepost 320) turn around and then enter the north entrance to the park from the westbound side.

Navajo Traffic Interchange (I-40 Milepost 325)

Work on the Navajo Interchange will consist of replacing the bridge deck. Work will be starting July 10 and will end August 8 2013. Traffic will not be able to cross the interstate to access the opposite side while work is being performed on the bridge. To access the opposite side motorists will need to travel east to the McCarrell Road Interchange (milepost 330) or west to the Pinta Road Interchange (milepost 320).

Chambers Traffic Interchange (I-40 Milepost 333)

Work on the Chambers Interchange will consist of replacing the superstructure and bridge deck. Work will start May 13 and will end July 9 2013. Traffic will not be able to cross the interstate to access the opposite side while work is being performed on the bridge. To access the opposite side motorists will need to travel east to the Sanders Interchange (milepost 339) or west to the McCarrell Road Interchange (milepost 330). View Photos.

Querino Traffic Interchange (I-40 Milepost 343)

Work on the Querino Interchange will consist of replacing the eastbound bridge deck. Work will be starting July 2 and will end August 8 2013. Traffic will not be able to cross the interstate to access the opposite side while work is being performed on the bridge. To access the opposite side motorists will need to travel east to the Pine Springs Interchange (milepost 346) or west to the Ortega Road Interchange (milepost 341).

 