ADOT, in association with the Federal Highway Association, evaluated improvements to I-19 to alleviate congestion and increase capacity within the corridor. The purpose of this project was to evaluate long-term improvements (2030) to I-19 between San Xavier Road and the I-10/I-19 traffic interchange.
ADOT and FHWA has evaluated the need for construction of the ultimate or long-term improvements, and identified those improvements in the Final Design Concept Report, to meet the needs of the traveling public:
Project History
I-19 Corridor Study: Interstate 10 to Pima/Santa Cruz County Line
ADOT completed a study in 2003 to identify transportation needs for the corridor through the year 2030. The study recommended long-term improvements through the year 2030 including additional lanes, auxiliary lanes and frontage roads in each direction of travel from San Xavier Road to I-10 with preferred short- and mid-term improvements, including additional interim travel lanes.
I-19 Project Assessment: San Xavier Road to Ajo Way
ADOT completed a Project Assessment (PA) in 2003. The purpose of the PA was to evaluate the feasibility of increasing the capacity of I-19.
I-10/I-19 Traffic Interchange
Construction of the traffic interchange was completed in 2004.
I-19 Design Concept Report: San Xavier Road to I-10
ADOT completed the Design Concept Report (DCR) in spring 2012. The report is available by link to this page.
Project Details
I-19 Corridor Study: Interstate 10 to Pima/Santa Cruz County Line
ADOT completed a study in 2003 to identify transportation needs for the corridor through the year 2030. The study recommended long-term improvements through the year 2030 including additional lanes, auxiliary lanes and frontage roads in each direction of travel from San Xavier Road to I-10 with preferred short- and mid-term improvements, including additional interim travel lanes.
I-19 Project Assessment: San Xavier Road to Ajo Way
ADOT completed a Project Assessment (PA) in 2003. The purpose of the PA was to evaluate the feasibility of increasing the capacity of I-19.
I-10/I-19 Traffic Interchange
Construction of the traffic interchange was completed in 2004.
|