|
Sanders Traffic Interchange |
| |
Project No.: |
191 AP 367 H4360 01C |
| |
Location: |
I-40 milepost 177 to 182 both EB and WB shoulders and milepost 182 to 190.4 just the WB shoulder. |
| |
Contractor: |
|
| |
Programmed Cost: |
$16,000,000 |
| |
Scope: |
This project will reconstruct the interchange at Sanders and I-40 |
| |
Expected Project
Duration: |
This project is currently in the planning phase with an anticipated bid advertisement date of 2013. |
| |
|
|
|
I-40 Lithodendron Bridges |
| |
Project No.: |
040 NA 300 H700801C 040-E-(205)A |
| |
Location: |
I-40 Milepost 300-303 |
| |
Contractor: |
FNF Construction, Inc. |
| |
Programmed Cost: |
$9,723,298.15 |
| |
Scope: |
Remove and replace four bridges. |
| |
Expected Project
Duration: |
Start Spring 2012 and complete Spring 2013 |
| |
|
|
I-40 Lithodendron to Petrified Forest |
| |
Project No.: |
040 NA 303 H785901C 040-E-(214)T |
| |
Location: |
I40 Milepost 303-311 |
| |
Contractor: |
Fisher Sand & Gravel Co. DBA Southwest Asphalt Paving |
| |
Programmed Cost: |
$7,149,000 |
| |
Scope: |
Milling the existing pavement and replacing it with new, bridge deck repair, removing and replacing guardrails and other related items. |
| |
Expected Project
Duration: |
Start June 2013 and complete September 2013 |
| |
|
|
I-40 Navajo, Chambers, Querino bridges |
| |
Project No.: |
040 AP 310 H771601C BR-040-E(207)T |
| |
Location: |
I-40 mileposts 325,333,343 |
| |
Contractor: |
Skanska USA Civil West Rocky Mountain District, Inc. |
| |
Programmed Cost: |
$2,999,998.91 (Programmed cost was bid with bridge project H745301C) |
| |
Scope: |
Replace the bridge decks for Navajo and Querino EB bridges and replace the bridge structure for the Chambers bridge. |
| |
Expected Project
Duration: |
Start Spring 2013 and complete Winter 2014 |
| |
|
|
I-40 Painted Desert Traffic TI |
| |
Project No.: |
040 AP 311 H745301C BR-040-E(206)T |
| |
Location: |
I-40 milepost 311 |
| |
Contractor: |
Skanska USA Civil West Rocky Mountain District, Inc. |
| |
Programmed Cost: |
$2,999,998.91 (Programmed cost was bid with bridge project H771601C) |
| |
Scope: |
Bridge replacement |
| |
Expected Project
Duration: |
Start Fall 2013 and complete Winter 2014 |
| |
|
|
SR 264 Steamboat to Burnside |
| |
Project No.: |
264 AP 426 H812001C STP-264A(215)T |
| |
Location: |
SR 264 Milepost 426-438 |
| |
Contractor: |
Sunland, INC. Asphalt $ Seal Coating |
| |
Programmed Cost: |
$5,081,817 |
| |
Scope: |
Repaving the roadway with new pavement, installing new cattle guards, shoulder build-up and other related work. |
| |
Expected Project
Duration: |
Start June 2013 and complete September 2013 |
| |
|
|
US 160 Anido Wash |
| |
Project No.: |
160 AP 455 H771301C STP-160-B(203)T |
| |
Location: |
US 160 Milepost 455 |
| |
Contractor: |
McDonald Bros. Construction, Inc. |
| |
Programmed Cost: |
$315,611.55 |
| |
Scope: |
Earthwork extension of an existing Concrete Box Culvert, erosion control at Anido Wash, removal and salvage of guardrail, removal and installation of wire fence. |
| |
Expected Project
Duration: |
Start Spring 2013 and complete Late Summer 2013 |
| |
|
|
US 160 Tuba City-Four Corners Highway |
| |
Project No.: |
160 NA 358 H811901C 160-A-(205)A |
| |
Location: |
US 160 Milepost 358-372 |
| |
Contractor: |
Fann Contracting, INC. |
| |
Programmed Cost: |
$6,571,999 |
| |
Scope: |
Milling the existing pavement and replacing with new, reconstructing guardrail, installing cattle guards and other miscellaneous work. |
| |
Expected Project
Duration: |
Start May 2013 and complete September 2013 |
| |
|
|