180 FUTS Trail |
| |
Project No.: |
TEA-180-A(002)A |
| |
Location: |
Ft Valley Road (US 180) From Navajo Road to West Valley Crest Street. |
| |
Contractor: |
Standard Construction Company |
| |
Programmed Cost: |
$2,753,000 |
| |
Scope: |
Construct new Flagstaff Urban Trail System along US 180. Includes new curb and gutter on portions of highway. |
| |
Expected Project Duration: |
Spring 2008 |
| |
| B-40, East Flagstaff Traffic Interchange |
| |
Project No.: |
AC-STP-TEA-089-C(002)B |
| |
Location: |
Intersection of US 89 and Business I-40, within the City of Flagstaff (milepost 418.10 to 419.10). |
| |
Contractor: |
Vastco, Inc. |
| |
Programmed Cost: |
$30,000,000.00 |
| |
Scope: |
The project components include reconstructing the US 89/I-40B interchange, adding a new signalized intersection at US 89 and Cummings Street into Flagstaff Mall, and widening of US 89. The Flagstaff Urban Trail System will also be rerouted through the new traffic interchange. |
| |
Expected Project
Duration: |
This project began in April 2006 and is expected to be completed by the Fall of 2008. |
| |
|
|
B-40, Pine Springs – Switzer Canyon |
| |
Project No.: |
40B CN 193 H6572 01 C |
| |
Location: |
Pine Springs (SR 40B MP 193.2) to Switzer Canyon (SR 40B MP 197.2) |
| |
Contractor: |
Fann Contracting Company |
| |
Programmed Cost: |
$4,102,000 |
| |
Scope: |
Project consists of milling and replacing old asphalt, adding a turn lane at the Woodlands Village Boulevard Intersection, minor curb gutter and sidewalk improvements and a culvert box extension. |
| |
Expected Project
Duration: |
This project is expected to be completed by early October 2008. |
|
Construction Alert |
| |
|
|
I-17, Southbound Airport Traffic Interchange to Munds Park Traffic Interchange |
| |
Project No.: |
017 CN 325 H6817 01 C |
| |
Location: |
Willard Springs Traffic Intersections (I-17, MP 325) to Flagstaff Airport Interchange (I-17, MP 337.15) |
| |
Contractor: |
Fann Contracting Company |
| |
Programmed Cost: |
$2,215,000 |
| |
Scope: |
Project consists of milling and repaving entire width of the roadway south bound from the Flagstaff Airport Interchange to the Willard Springs Interchange. There will also be some guardrail work and replacement of some cement sections under the roadway. This project has been extended another 1.5 miles south on I-17 and will end around mile post 323. |
| |
Expected Project
Duration: |
This project is expected to be completed by late July early August 2008. |
|
Construction Alert |
| |
|
|
SR 64 Passing Lanes |
| |
Project No.: |
064-A-NFA |
| |
Location: |
Approximately two miles north of the I-40 / SR 64 junction, just outside the city limits of Williams (Mile post 187.9 to 189.4) |
| |
Contractor: |
Haydon Building Corp |
| |
Programmed Cost: |
$2,200,000.00 |
| |
Scope: |
Project components include widening the existing two lane highway to provide a new northbound passing lane and lengthening the existing southbound passing lane. |
| |
Expected Project Duration: |
Construction began April 14, 2008 and is expected to be completed by October 2008. |
| |
|
|
| SR 179 Village of Oak Creek to Y (Project 1 and 2) |
| |
Project No.: |
STP-TEA-A(001)B and STP-TEA-A(002)B |
| |
Location: |
Project 1 is from MP 304.5 (1 mile south of Village of Oak Creek) to MP 310.4 (Back o’ Beyond) and
Project 2 is from MP 310.4 to 313.4 (the “Y”) in the City of Sedona. |
| |
Contractor: |
Southwest Asphalt Paving (Project 1) |
| |
Programmed Cost: |
Project 1 $36,114,000
Project 2 $51,750,000 |
| |
Scope: |
Projects consist of complete rebuild of highway to a multimodal, two lane parkway. |
| |
Expected Project Duration: |
Project 1 Fall 2006 to Spring 2008
Project 2 Fall 2008 to Fall 2010 |
| |
|
|
US 89 - Bitter Springs to Page |
| |
Project No.: |
089 CN 524 H 5840 01 C |
| |
Location: |
Junction of US 89 and 89A MP 523.5 (Bitter Springs) to US 89 MP 531.20. |
| |
Contractor: |
FNF Construction Inc. |
| |
Programmed Cost: |
$4,265,000 |
| |
Scope: |
Project consists of milling and repaving the full width of roadway and guardrail end treatments. |
| |
Expected Project Duration: |
This project is expected to be completed August 2008. |
|
Construction Alert |
| |
|
|
| Documents are posted as they become available in PDF format, which requires Adobe Reader to view. |