Safford Construction ORG 8430

I-10 San Simon – State Line

    Project No.: 010 CH 384 H779501C
      010-F-(205)T
    Location: Cochise County on I-10 approx. 5 miles east of San Simon
    Contractor:

FANN Contracting Inc.

    Awarded: November 16, 2012
    Description:

The work consists of removing the existing Asphaltic Concrete (AC) by milling and replacing it with new AC and Asphalt-Rubber Asphaltic Concrete Friction Course. Additional work includes upgrading the existing guardrail end treatments, removing concrete from a bridge deck and replacing it with micosilica modified concrete overlay, replacing pavement markings, and other misc. work.

    Duration: The time allowed for the completion of the work included in this project will be 120 working days.
       

US 70 Gila River Bridge at Bylas

    Project No.: 070 GH 291 H691001C
      BR-STP 070-A(204)A
    Location:

Graham County on US 70 approximately 5 miles west of Bylas. Work begins at milepost 291.81 and extends easterly to milepost 293.74 for an approximate length of 1.9 miles.

    Contractor: FNF Construction, Inc.
    Awarded: November 18th, 2011
    Description:

The work includes removing the existing twenty three-span steel girder bridge and replacing it with a fifteen-span precast prestressed concrete AASHTO.

Type VI girder bridge. In addition, the project includes roadway approach widening, intersection improvement, guardrail reconstruction, berm construction, irrigation line installation, pavement markings placement and other miscellaneous work.

    Duration: The time allowed for the completion of the work included in this project will be 380 working days.
       
       

US 191 Bowie Junction – Safford Highway Segment V

    Project No.: 191 GH 100 H818501C
      STP-191-B(201)A
    Location: Graham County on US 191 at milepost 100.59 to milepost 104.52, approximately 15 miles south of Safford
    Contractor: CKC Construction & Materials LLC
    Awarded: December 17, 2010
    Description: The work includes the construction of two new northbound lanes east of the existing roadway with asphaltic concrete and asphaltic rubber friction course; construction of turnouts and reconfiguring the “T” intersection with SR 266; extend five reinforced concrete box culverts; extend 13 existing pipe culverts; construct 14 new pipe culverts; construct 23 new lateral storm drains and catch basins; overlay the existing pavement with asphaltic concrete and asphaltic rubber friction course; erosion control; seeding; signing; pavement marking; and other related work.
    Duration: The Department-Determined Construction Phase Time for substantial completion of the work shall be 500 calendar days.
       

US 191 Cold Creek Canyon Bridge to Old Safford Road

    Project No.: 191 GE 154 H823101C
      BR-STP-191-C(212)T
    Location: Greenlee County on US 191 between milepost 154.63 and 159.76, approximately 8 miles south of the Town of Clifton
    Contractor: FNF Construction, Inc.
    Awarded: October 2012
    Description: The work encompasses constructing new five span southbound Cold Creek Canyon Bridge on new alignment, scour retrofitting existing northbound Cold Creek Canyon Bridge, and replacing bridge barrier on southbound Rattlesnake Canyon Bridge. The work also includes pavement preservation along both NB and SB throughout the length of the project. Additional work includes constructing retaining wall, replacing guardrail and guardrail end terminals, replacing pavement markings, signing, and other miscellaneous work.
    Duration: The time allowed for the completion of the work included in this project will be 220 working days.
       
 


Benson Construction ORG 8431

I-10 & SR 90 Traffic Interchange (TI)

    Project No.: 010 CH 300H650401C
      NH-STP-HSIP-TEA-010-E(200)N
    Location: Cochise County on I-10 at the State Route 90 Traffic Interchange near the City of Benson
    Contractor: Borderland Construction Co., Inc.
    Awarded: September 1, 2010
    Description:

   Project Web site
The project will reconstruct the I-10/SR 90 TI overpass structures, SR 90 below the overpass, entrance and exit ramps in both directions, realign and reconstruct I-10 mainline west of the TI, construct three access roads (W. Dark Star Road, N. Vidal Trail and W. Calvary Lane), drainage improvements, lighting, utility relocations, signing and marking, and other related work.
    Duration: The time allowed for the completion of the project is 500 working days.
       

State Route 90 San Pedro Bridge Replacement

    Project No.: 090 CH 328 H600501C
      BR-NH-090-A(201)A
    Location: Cochise County on SR 90 about 8 miles east of Sierra Vista
    Contractor: Ames Construction, Inc.
    Awarded: August 2012
    Description: The work consists of removing the existing San Pedro River bridge and replacing it with a new three span prestressed concrete girder bridge, raising the vertical profile of the road, replacing guardrail and guardrail terminals, pavement markings and related items.
    Duration: The time allowed for the completion of the work included in this project will be 400 working days.
       

US 191B Douglas – Rodeo Highway

    Project No.: 191B CH 000 HX23801C
      STP-191-N(202)
    Location: Cochise County on US 191B between MP 0.0 and MP 1.08 within the City of Douglas
    Contractor: K E & G Construction, Inc.
    Awarded: October 2012
    Description: The work consists of placing micro-surfacing and other improvements near the port of entry including a metering traffic signal, signing, pavement markings and other related work.
    Duration: The time allowed for the completion of the work included in this project will be 135 working days.
       

City of Sierra Vista Milling 7th Street – SR 90 Bypass & Willcox Drive, 7th Street – Calle Portal

    Project No.: **0000 CH SVS SZ02501C / STP-SVS-0(212)T
      *0000 CH SVS SS98901C / STP-SVS-0(211)T
    Location: *Cochise County within the City of Sierra Vista on Willcox Drive, from 7th Street to Calle Portal & **7th Street from Buffalo Soldier Trail to SR 90 Bypass
    Contractor: K E & G Construction, Inc.
    Awarded: December 2012
    Description: *The work consists of milling full depth of pavement, furnishing and placing asphaltic concrete, pavement marking, resetting of the frame and cover of survey monuments, sewer manholes, and other related work. **The proposed work includes partial milling, furnishing and placing asphaltic concrete, pavement marking, resetting of the frame and cover of survey monuments, sewer manholes and other related work.
    Duration: The time allowed for the completion of the work included in this project will be 120 working days.
       
 

 