|
|
Safford District Current Projects
Safford Construction ORG 8430
| Safford 8th Avenue Bridge |
| |
Project No.: |
000 GH GGH SB41601C / BR-GGH-0(007)A |
| |
Location: |
North of the City of Safford in Graham County at the 8th Avenue Bridge over the Gila River |
| |
Contractor: |
AMES Construction, Inc. |
| |
Description: |
The project work will include the construction of a new bridge crossing over the Gila River and re-align both roadway approaches. The new structure will be located adjacent to an upstream of the existing structure. Additional work includes placement of pavement markings, signs, seeding, and other related work. The Construction Supervisor of this project is Paul David, Senior Resident Engineer, located in the Safford Construction Office, phone 928.432.4936. Work on the project began in April 2009. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project is 215 working days. |
| |
|
|
|
| Safford – Bryce Road at Peterson Wash |
| |
|
Project No.: |
0000 GH GGH SH27701C |
| |
|
|
STP-GGH-0(006)A |
| |
|
Location: |
Graham County on Safford Bryce Road |
| |
|
Contractor: |
|
| |
|
Awarded: |
Bid Opening Friday, October 30, 2009 |
| |
|
Description: |
The proposed work consists of removal of existing pavement; raising the vertical profile of the road; asphaltic concrete pavement; aggregate base course; earthwork; concrete box culvert; extension including headwalls and apron; installing new guardrail and guardrail end terminals; signing and striping; erosion control and other related work. |
| |
|
Duration: |
Time allowed for the completion of this project is 110 working days. |
| |
|
|
|
| |
|
|
|
| SR 75 York Valley Pedestrian Walkway |
| |
|
Project No.: |
075 GE 395 H606001C |
| |
|
|
ARRA-075A(001)A |
| |
|
Location: |
Greenlee County on State Route 75 within the Town of York Valley between Milepost 395.77 and 396.25 |
| |
|
Contractor: |
Bison Contracting Co., Inc. |
| |
|
Awarded: |
October 16, 2009 |
| |
|
Description: |
The project consists of constructing a six foot wide pedestrian walkway. The improvements will include a new drainage pipe, a box culvert extension, concrete barrier, metal handrail, asphaltic concrete, signing and other related work. |
| |
|
Duration: |
Time allowed for the completion of this project is 85 working days. |
| |
|
|
|
US 191 Black Hills Road (Back Country Byway) |
| |
|
Project No.: |
191 GE 159 H643201C |
| |
|
|
ARRA 191-C(202)A |
| |
|
Location: |
Greenlee County US 191 MP 159.40 near the three-way intersection of US 191, SR 75 and SR 78 |
| |
|
Contractor: |
CKC Construction & Materials, LLC. |
| |
|
Description: |
Work consists of improvements between MP 159.40 and 16.10, removing, re-grading and relocating the existing Back Country Byway and constructing a new intersection with US 191 including grading a new eastern turnout. Other proposed work includes a median cross over connection and dedication left-turn and right-turn lanes. Also included are drainage and guardrail modifications, Class II seeding, pavement marking and signage and other related items of work. |
| |
|
Duration: |
Time allowed for the project is 120 working days. |
| |
|
News Release: |
Reduced Speed Limits On
Black Hills Back Country Byway |
| |
|
|
|
US 191 Coronado Trail MP 173.6 |
| |
|
Project No.: |
191 GE 173 H710001C |
| |
|
|
ARRA-191-C(203)A |
| |
|
Location: |
US 191 between Milepost 173.6 and 182.6 in Greenlee County |
| |
|
Contractor: |
Bison Contracting Co., Inc. |
| |
|
Awarded: |
September 18, 2009 |
| |
|
Description: |
The proposed work includes culvert extensions, new culvert installations, new embankment curb, drainage ditch improvements and new down drains to improve drainage in the area. |
| |
|
Duration: |
Time allowed for the completion of the project is 80 working days |
| |
|
News Release: |
Drainage Improvements Begin on US 191 Lower Coronado Trail |
| |
|
|
|
US 191 Discovery Park Blvd. – Relation Street Sidewalk |
| |
|
Project No.: |
191 GH 118 H574401C |
| |
|
|
ARRA-TEA-191-B(001)A |
| |
|
Location: |
Graham County on US 191 within the City of Safford between Milepost 118.83 and MP 120.32 (1.49 miles) |
| |
|
Contractor: |
|
| |
|
Awarded: |
Bid Opening Thursday, November 19, 2009 |
| |
|
Description: |
The work consists of constructing sidewalk between Discovery Park Boulevard and Relation Street. The improvements will also include new sidewalk ramps, curb, driveways, metal handrail, mailbox relocations, signing, minor utility adjustments and other related work. |
| |
|
Duration: |
Time allowed for the completion of this project is 120 working days. |
| |
|
|
|
| |
Benson Construction ORG 8431
I-10 East Benson-Johnson Road |
| |
|
Project No.: |
010 CH 307 H682201C |
| |
|
|
ARRA-010-F(201)A |
| |
|
Location: |
Cochise County just east of Benson, the project begins at MP 307.9 and extends east for 14 miles. |
| |
|
Contractor: |
FNF Construction, Inc. |
| |
|
Awarded: |
June 2009 |
| |
|
Description: |
The project includes milling of the existing pavement and placement of AC ¾” End Product, Special Mix and AR-ACFC; milling and filling various locations to improve the smoothness of the roadway; extension of three concrete box culverts; removing and replacing guardrail; placing pavement markings; rumble strips and other related work.
Consultant Administered by Tristar Engineering & Management, Inc. |
| |
|
Duration: |
Time allowed for the completion of the project is 125 working days. |
| |
|
|
|
I-10 EB Luzena to Bowie |
| |
|
Project No.: |
010 CH 357 H763801C |
| |
|
|
ARRA-010F(203)A |
| |
|
Location: |
Cochise County I-10 eastbound MP 57.7 to MP 362.6 13 miles east of Willcox |
| |
|
Contractor: |
FNF Construction, Inc. |
| |
|
Awarded: |
June 2009 |
| |
|
Description: |
Work consists of milling existing pavement and replacing with Asphaltic Concrete (3/4”) End Product and AR-ACFC.
Consultant Administered by CEI-Consultant Engineering, Inc |
| |
|
Duration: |
Time allowed for the project is 40 working days. |
| |
|
|
|
SR 80 Double Adobe-Douglas |
| |
|
Project No.: |
080 CH 349 H781101C |
| |
|
|
ARRA-080-A(202)A |
| |
|
Location: |
Cochise County on SR 80 beginning approximately 14 miles west of Douglas, at MP 349, and extending eastward to milepost 363. |
| |
|
Contractor: |
D & O Contractors, Inc. |
| |
|
Awarded: |
June 2009 |
| |
|
Description: |
Work consists of removal of existing fencing, and installation of new barbed wire fencing along both edges of the SR 80 right-of-way. The work also includes installation and removal of gates, and other related work. |
| |
|
Duration: |
Time allowed for the completion of this project is 115 working days. |
| |
|
|
|
SR 80 Douglas Strategic Motor Carrier Station |
| |
|
Project No.: |
080 CH 364 H624301C |
| |
|
|
CBI-080-A(009)B |
| |
|
Location: |
Cochise County at the intersection of SR 80 and US 191 in Douglas |
| |
|
Contractor: |
Haydon Building Corp. |
| |
|
Description: |
Work consists of the construction of a yard and scales for vehicle weight and safety inspection for the State of Arizona, Motor Vehicle Division. The work consists of constructing a yard with Portland cement concrete paving, truck scales, scale hours, drainage, water, sewer; lighting, gales, security walls, fences, utility relocations and other incidental work. |
| |
|
Duration: |
Time allowed for this project is 160 working days. |
| |
|
|
|
SR 80 Tombstone Streets |
| |
|
Project No.: |
080 CH 316 H767501C |
| |
|
|
ARRA-080-A(201)A |
| |
|
Location: |
Cochise County on SR 80 at MP 316.60 and proceeding easterly through Tombstone to MP 317.56 |
| |
|
Contractor: |
Combs Construction Co. |
| |
|
Description: |
This Pavement Preservation project includes milling 3” of the existing asphalt and replacing with 3” AC ¾” mix and 1/2” ACFC along SR 80, milling and replacing 2” existing AC with 2” AC ¾” mix and Fog Coast along Sumner and Fremont Streets, median improvements, restriping, adjusting valve covers, survey monuments, and other related work. |
| |
|
Duration: |
Time allowed for the completion of the work included in this project will be 50 working days. |
| |
 |
Traffic Alert: |
September 18, 2009 |
| |
|
|
Roadway Improvements on State Route 80 in Tombstone to be Complete Early October |
| |
|
|
|
| SR 82 San Pedro River Bridge |
| |
|
Project No.: |
082 CH 061 H749701C |
| |
|
|
STP-082-A(200)A |
| |
|
Location: |
Cochise County on State Route 82 at the San Pedro River Bridge at Milepost 61.2 approximately 8 miles west of the City of Tombstone |
| |
|
Contractor: |
Bid Opening October 23, 2009 |
| |
|
Awarded: |
|
| |
|
Description: |
The proposed scour retrofit work consists of constructing reinforced concrete slab at the piers and abutments, repairing the west abutment and performing other related work. |
| |
|
Duration: |
The time allowed for the completion of the work is 95 working days. |
| |
|
|
|
| SR 92 Carr Canyon to Hunter Canyon |
| |
|
Project No.: |
STP-092-A(001)B / H459601C |
| |
|
Location: |
Project Map |
| |
|
Description: |
Project Web site |
| |
 |
Traffic Alert: |
November 23 - 29 |
| |
|
|
|
US 191 Sunsites at High Street |
| |
|
Project No.: |
191 CH 048 H650901C |
| |
|
|
ARRA 191 A(200)A |
| |
|
Location: |
Cochise County about 18 miles southeast of the I-10 intersection at MP 48.36 and ends at MP 48.94 |
| |
|
Contractor: |
CKC Construction and Materials LLC |
| |
|
Description: |
Work consists of pavement widening to construct a southbound right turn lane and northbound left turn lane to High Street. Additional work includes installing new pipe culverts, relocating existing channel from the west side of the highway to the east side, signing and pavement markings, reconstructing turnout, slope improvements and other related items. The project will begin in June 209. |
| |
|
Duration: |
Time allowed for the completion of this project is 70 working days. |
| |
|
|
|
| |
|