Project Activities

The list of project development activities cover 3 main areas: Stage I, Stage II through Final Project Specifications and Estimates (PS&E), and construction. They are covered in more detail below:

Stage I (15% Preliminary Engineering)

Attend the Post Award Meeting.

Wait for authorization/Notice to Proceed if requesting federal reimbursement for scoping and environmental.

Attend project scoping kick-off meeting and determine who will bid the project.

Prepare initial and final scoping document (also called Project Assessment).

Deposit ADOT Preliminary Engineering (PE) funds a into preliminary engineering account when the project scoping document is submitted. The account covers the cost of ADOT staff review.

Prepare documentation for the environmental clearance. All documentation must be prepared in ADOT/Federal Highway Administration (FHWA) format.

Obtain approval for the final Project Assessment and the environmental document. After this step, you must get a notice to proceed from ADOT to begin incurring design costs if you intend to request reimbursement for those costs.

 

Stage II through Final PS&E

Do not begin design until you get a written notice to proceed from the ADOT Project Manager. Doing so will result in a portion of your costs not being eligible for reimbursement. Any design work anticipating the use of federal funds must be identified as such in the project application.

Attend project design kick-off meeting and field review.

Submit Stage II - 30% Design plans, cost estimate, and materials/geotech reports for review. If federal money is used for design, the project cannot proceed past Stage II until environmental approval is granted.

Submit Stage III - 60% Design plans for review and final materials memo. Specifications are due at this time along with all details.

Finalize the Joint Project Agreement (JPA). ADOT will prepare the JPA for local and state execution. Deposit local funds into the construction account.

Submit Stage IV - 95% Design plans.

Obtain utility and right of way clearances.

Submit Final PS&E - 100% Design plans and request for federal funding for construction.

 

Construction

Do not begin construction until you get a written notice to proceed from the ADOT Project Manager.

Advertise for bids. ADOT will perform this function unless the sponsor has certification acceptance or FHWA/ADOT approval to self-administer the project.

Project construction. ADOT will administer construction unless the sponsor has certification acceptance or FHWA/ADOT approval to self-administer the project.

 