Utilities Clearance
Each Transportation Enhancement
project is required to have utility clearance before
it goes to bid advertisement. Project sponsors are
responsible for providing the documentation for
such clearance.
During design, project sponsors send the 30%, 60%,
and 95% plans to the various companies having utilities
in the project area to determine if there are any
utility conflicts. Such coordination will be documented
in a report called a Utility Packet; followed by
a separate clearance memo stating that there are
no utility conflicts and, with regard to utilities,
the project is ready for bid advertisement.
If the sponsor has Certification Acceptance, the Utility Packet can follow their own formatting. If the sponsor does not have Certification Acceptance, the Utility Packet must conform to ADOT requirements.
|