Interstate 10 (Ruthrauff Road to Prince Road) Widening Project

   

Construction Information

Construction began in September 2011. The project is scheduled to be completed by late 2013. Access to all properties in the construction area will be maintained, although drivers may need to use alternate routes to reach destinations along the construction zone. Periodic lane or other closures could occur to allow short-term project construction needs.

ADOT will provide information about traffic impacts through roadway signs, regular traffic alerts, news media announcements and this website.

Construction Timeline:

INITIAL PREPARATIONS:
Click area to expand/collapse.

This work began in September 2011.

  • I-10, Prince Road and project-area streets remain open with minor changes and impacts to traffic in limited areas

PHASE ONE: 
Click area to expand/collapse.

This first phase of major construction began March 12, 2012, and is anticipated to last until early 2013.

I-10:

  • I-10 remains open with three lanes in each direction

Frontage Roads:

  • Westbound frontage road between Freeway Industrial Loop, just north of Miracle Mile and Ruthrauff Road is closed
  • Westbound frontage road traffic, south of Prince Road, will be rerouted to westbound I-10 and back onto the westbound I-10 frontage road at Ruthrauff Road

Prince Road:

  • Closed at I-10 in both directions.
  • Westbound entrance ramp at Prince Road interchange is closed

Runway Drive:

  • Runway Drive east of the Prince Road traffic interchange will close from Prince Road to Weymouth Street for approximately 60 days beginning May 1, 2012

How to Get Around:

  • I-10 open
  • I-10 access open at: Miracle Mile and Ruthrauff Road/El Camino del Cerro interchanges
  • East of I-10, north/south travel: La Cholla Boulevard, Romero Road, Flowing Wells Road and Fairview Avenue remain open
  • East/west travel: Ruthrauff Road, El Camino del Cerro, Wetmore Road and Miracle Mile remain open
PHASE TWO: 
Click area to expand/collapse.

This second phase of construction is anticipated to last for approximately one year beginning early 2013. The project will be completed by late 2013.

I-10:

  • Three lanes remain open in each direction
  • Crews will work on the westbound side of I-10
  • Eastbound and westbound traffic will both travel on three lanes each of eastbound I-10

Frontage Roads:

  • Westbound frontage road between Freeway Industrial Loop, just north of Miracle Mile and Ruthrauff Road closed
  • Westbound frontage road traffic, south of Prince Road, will be rerouted to westbound I-10 and back onto the westbound I-10 frontage road at Ruthrauff Road
  • Eastbound frontage road open

Prince Road:

  • Closed at I-10 in both directions
  • Entrance and exit ramps for I-10 closed, EXCEPT new eastbound I-10 exit ramp will be open
  • Open for eastbound and westbound traffic from Runway Drive/Romero Road east

How to Get Around

  • I-10 open
  • I-10 access: Miracle Mile interchange, Ruthrauff Road and El Camino del Cerro interchange open
  • East of I-10: north/south travel - La Cholla Boulevard, Romero Road, Flowing Wells Road and Fairview Avenue open
  • West of I-10: north/south travel - Eastbound frontage road open Silverbell Road, west of I-10 to Grant open
  • East/west travel: Ruthrauff Road, El Camino del Cerro, Wetmore Road and Miracle Mile open

Your thoughts, opinions and ideas are important to ADOT. We encourage public participation and look forward to hearing from you by phone or email.

Project Information

855.712.8530

 

Subscribe to receive future project updates  Keep informed about this project, subscribe to receive future project updates by email.

    Arizona Department of Transportation    
   Disclaimer & Privacy Statement  |   Contact ADOT