Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
Loop 202 (South Mountain Freeway)
  
Loop 202 (South Mountain Freeway)
Library
All ADOT projects move ahead based on a series of important reports and studies. Below you’ll find links to documents related to the South Mountain Freeway project.
  Frequently Asked Questions
Divider

Project History

Background
In 1985, Maricopa County voters approved funding for the Maricopa Association of Government’s Regional Freeway System, which included a South Mountain Freeway connection with Interstate 10 in the Southeast Valley with Interstate 10 in the West Valley. The State Transportation Board approved an alignment for the South Mountain Freeway in 1988, running east and west along Pecos Road and then turning north between 55th and 63rd avenues. A state-level Environmental Assessment (EA) was completed in 1988. More | Close

Due in part to a funding shortfall, the Arizona Department of Transportation was unable to develop 76 miles of planned freeways, including the South Mountain Freeway segment. The unfunded corridor, however, remained part of the planned Regional Freeway System.

In 2001, ADOT and the Federal Highway Administration (FHWA) began an updated study through an Environmental Impact Statement (EIS) to determine if such a freeway was still needed, to meet the needs of the traveling public, where it should be located, and potential environmental, social and economic effects. The updated EIS was required due to the many changes in the study area since the original 1988 Environmental Assessment was completed.

A final decision on the alignment of the South Mountain Freeway – including a decision on if the roadway will be constructed – will be made at the conclusion of the environmental process.

1988 Environmental Assessment
As presented in the 1988 Environmental Assessment, a freeway would connect Interstate 10 south of Phoenix with Interstate 10 in the West Valley, following an east-west alignment along Pecos Road, through the western tip of South Mountain Park, then north to Interstate 10 between 55th and 63rd avenues. The north-south leg of the freeway would pass near the community of Laveen and through agricultural lands within the city of Phoenix. After it passes South Mountain Park and turns to the east, the freeway would pass through the Ahwatukee Foothills community, following an alignment along Pecos Road.

The current study process is evaluating the 1988 route, as well as a full range of alternative routes and the consequences of taking no action on the proposed roadway.

Environmental Impact Statement
An Environmental Impact Statement presents information as to how a proposed project and its alternatives may affect the natural and built/social environment. Elements of the natural environment that are often studied include air quality, wildlife and wildlife habitat, water resources, and wilderness. Elements of the social/built environment that are often studied include farmlands, history and archaeology, noise, parks and recreation, communities, and aesthetics. More | Close

Environmental Impact Statements (EIS) are required for all major federal actions (or those involving federal monies) that could have a significant effect on the environment as required by the National Environmental Policy Act (NEPA).

National Environmental Policy Act

NEPA was signed into law on January 1, 1970, in response to public sentiment that federal agencies should take a lead in providing greater protection for the environment. NEPA is the basic national charter for protection of the environment. It sets policy goals and provides a means for carrying out the policy. Additional NEPA facts include:

NEPA procedures are intended to insure that environmental information is available to public officials and citizens before decisions are made and actions taken. The intent is to help public officials make decisions that are based on an understanding of environmental consequences, and take actions that protect, enhance, and restore the environment.

NEPA is designed to encourage and facilitate public involvement which affects the quality of the human environment.

NEPA is designed to identify and assess reasonable alternatives to proposed actions. The intent is to diminish adverse environmental effects and to protect the environment.

NEPA is designed to be both proactive and reactive. It requires that reasonable alternatives be considered and it requires that the human environment be restored when possible following environmental damage.

NEPA encourages federal agencies to use a systematic, interdisciplinary approach to agency decision-making.

For more information on NEPA and the Federal Highway Administration's involvement, visit the FHWA Environmental Review Toolkit site.

Environmental Impact Statement Process

The first step in preparing the EIS for this project was to determine whether there was a need for transportation improvement in the corridor. Based on recent traffic analysis and public comment received since July 2001, there appears to be a purpose and need to continue the study and complete the EIS. Analysis of conservative expectations for population growth, future traffic and mobility needs in the Valley shows that it is only prudent to assume that additional transportation options will be required.

The EIS study process will examine the potential social, economic and environmental impacts of a variety of alternatives – including the 1988 route and the no-build option – along with ways to lessen those impacts. Additional alternatives identified by local community groups, organizations and interested citizens are also being considered by the project team. At meetings held in 2003, the public was shown the alternatives advanced for further study and shared questions, comments and concerns with members of the study team.

A key component of the study process includes extensive public involvement and ongoing opportunities for community members to express opinions and concerns. Local residents, community leaders, governmental agencies and elected officials continue to be involved in the decision-making process. The project team will also continue to meet with village planning committees, service organizations, homeowners associations, other neighborhood groups throughout the study area, and the Gila River Indian Community. In addition, a South Mountain Citizens Advisory Team (CAT) composed of a diverse group of organizations effected by the South Mountain Freeway Corridor has been established and meets regularly.

The goal of the process is to receive extensive, high-quality public input on how to meet the region's existing and future transportation needs in accordance with the Regional Transportation Plan.

The goal of this study is to determine the best way to serve the transportation and mobility needs of people in the entire Phoenix metropolitan region.

Why does this process take so long?

This is a complex and important research project. Engineers, researchers and environmental scientists must determine the impacts of new information that is discovered throughout the process. This process is one of discovery. Therefore, much of the data for this project must be updated to include the best available, most accurate information. That said, ADOT and FHWA are committed to concluding this study as quickly as possible and coming to resolution on the future of the proposed South Mountain Freeway.

Project Alternatives
Alternatives for Further Study

The Study Team began with more than 30 alternatives to evaluate for the South Mountain Freeway corridor. Those alternatives comprised the two segments of the proposed freeway: east and west. The split between the east and west alternatives selected for further study lies just east of 59th Avenue and south of Elliot Road. More | Close

The western section was narrowed to three alternatives: W55, W71 and W101. The W55 alternative would connect to I-10 at roughly 55th Avenue, W71 at 71st Avenue, and W101 at the existing Loop 101/I-10 system interchange.

In response to budget concerns and impacts of the proposed freeway, two changes resulted. One of these changes was to shift the W55 alignment between Lower Buckeye road and I-10 to connect at 59th Avenue. This shift results in less of an impact to the service traffic interchanges on I-10 from 75th Avenue to 43rd Avenue as well as to money saved through ramp reconfigurations.

There is one action alternative in the eastern section, E1. It generally follows the same alignment as in the 1988 Design Concept Report and connects to I-10 at the Pecos Road/I-10/Loop 202 Santan Freeway system interchange. ADOT remains committed to evaluating other alternatives in the eastern segment should any become available for study.

Identifying the Alternatives

Numerous potential alternatives have been suggested. Early in the study, workshops were held with citizens; civic organizations; the Ahwatukee, Estrella, Laveen and South Mountain village planning committees; Maricopa County Farm Bureau; and the Southwest Mayors and Managers group. Participants were invited to draw alignments on study area maps and aerial photos, and to indicate cultural or environmental constraints. From these workshops more than 30 potential alternatives were identified for the entire corridor.

These 30 public alternatives were grouped into corridors for review by the technical team, which then narrowed them to nine “Technical Alternatives.” The nine alignments were presented to the potentially affected local jurisdictions, including Tolleson, Avondale, Goodyear, Chandler, Phoenix, Maricopa County, MAG and the Gila River Indian Community (GRIC).

Where Would it Connect to I-10 East?

If built, the South Mountain Freeway would likely connect to I-10 east at the current interchange of I-10 and Loop 202 (Santan Freeway). The only option available at this time would have a freeway follow the Pecos Road alignment, remaining just north of the boarder between Phoenix and the GRIC. The Pecos Road alignment was first proposed in the mid-1980s.

Gila River Indian Community

Since the beginning of the study in 2001, ADOT and FHWA have been working with the GRIC to determine if a portion of a freeway might be located on community land to the south of Pecos Road. To date, no GRIC options have been approved by the community for further study.

The GRIC Tribal Council has opposed construction of the South Mountain Freeway on tribal lands since August 2000 when a formal resolution was approved. That resolution was readopted by the Tribal Council in 2005.

GRIC has sole authority to decide if and where a freeway might be studied or built on its land. Therefore, if an eastern preference must be identified without GRIC alternatives, options would include either the Pecos Road alignment or not building the South Mountain Freeway.

Is Not Building the Freeway Really an Option?

Not building a freeway remains an option. If this option is selected, the proposed project would not take place and the environmental effects from taking no action would be evaluated. It is possible, however, that a new study for the area could be initiated at some point in the future. While ADOT has been charged to study the proposed South Mountain Freeway by the Maricopa Association of Governments, the regional transportation planning body, ADOT has not taken a formal position on the roadway and will not do so until the study is complete and all alternatives evaluated.

Background on the Alternatives

Need Exists for South Mountain Freeway

An extensive analysis of population trends, land use plans and travel demand shows clearly that there is a traffic problem in the Southwest and Southeast areas of the Valley. Congestion will continue to worsen if transportation plans fail to appropriately address increases in population and vehicles.

At this point in the study process it has been determined that while planned transit and roadway improvements must be part of the solution to the Valley's future transportation needs, a purpose and need exists to include a new freeway in the South Mountain Corridor. The no-build option, however, remains an alternative and is being studied at the same level of detail as the action alternatives.

The process of identifying alternative routes for the South Mountain Freeway has included local governments, businesses, MAG, the GRIC and the general public. The process began with a public “scoping” phase, during which a number of alternatives, enhanced transit options and several conceptual alignments were proposed.

Chronology and Timeline
A brief chronology of the South Mountain Transportation Corridor, from its inception to the present. More | Close

  • 1983 The Maricopa Association of Governments (MAG) prepares planning studies for the Phoenix metropolitan area that identify corridors for an integrated freeway network. The South Mountain Transportation Corridor is defined as a roughly two-mile wide corridor from I-10 near 51st Avenue, around South Mountain, to I-10 near Chandler Boulevard.
  • 1985 Maricopa County voters approve a half-cent sales tax to fund construction of the MAG Regional Freeway System, including a 22-mile freeway connecting I-10 in Chandler with I-10 in west Phoenix.
  • 1988 A Location/Design Concept Report and a state-level Environmental Assessment are completed for the South Mountain Freeway, designating an alignment along Pecos Road and the Gila River Indian Community border and north to I-10 between 55th and 63rd avenues. This refined corridor is adopted by the State Transportation Board.
  • 1994 Due to a funding shortfall, ADOT identifies 76 miles of planned freeways as "unfunded segments" and later drops some of those segments from the system. The South Mountain Transportation Corridor is designated for potential development as a toll road.
  • 1996 A consortium of private companies proposes to build the South Mountain Freeway as a toll road. The consortium would later withdraw its proposal, saying the project was not financially feasible. The South Mountain Transportation Corridor remains a part of the MAG Regional Freeway System but designated as "unfunded."
  • Next Steps Flowchart1999 ADOT announces plans to accelerate completion of the entire Regional Freeway System by seven years. The acceleration plan includes an unspecified portion of the South Mountain Transportation Corridor, which remains largely unfunded.
  • 2000 In anticipation of initial construction of the South Mountain Freeway, the City of Phoenix conducts a local study of Ahwatukee Foothills area transportation needs that includes an assessment of freeway options.
  • 2001 ADOT begins preparation of a new Location/Design Concept Report and EIS to examine a broad range of alternatives to the 1988 South Mountain Freeway concept.
  • Summer/Fall 2001 The South Mountain Corridor Team collects base information and issues on the transportation corridor.
  • Fall/Winter 2001 South Mountain Corridor Team determines that there is a purpose and need to continue the EIS study.
  • Fall 2003 ADOT, FHWA, and the U.S. Army Corp of Engineers concur on the Alternatives Screening. Three build alternatives plus options are carried forward into the EIS for more detailed analysis.
  • Fall 2004 Voters approved funding MAG's Regional Transportation Plan – including South Mountain Freeway.
  • June 2006 ADOT announces the W55 (55th Avenue) Alternative as the “preliminary preferred alternative” based on community input, economic impacts, and traffic information.
  • 2007 Public information meetings were held throughout the year to communicate with and receive input from members of the community.
  • 2009 MAG updates the Regional Transportation Plan, includes reducing the South Mountain Freeway’s footprint to eight lanes with a connection to I-10 at 59th Avenue.
  • 2011 Draft EIS and public hearings are expected to occur following a final review of the document by the Federal Highway Administration. Final decision on the South Mountain Freeway will follow the release of the Draft EIS and public hearings and comment.

When the Draft EIS is released to the public, it will detail the options considered in the Southwest Valley and describe the reasons why the 59th Avenue Alternative was selected as the preferred option for the Western Section. The Draft EIS will also detail the Pecos Road option being considered in the Eastern Section area of the study. If other options become available to study, the process will take those into account. The Draft EIS also will discuss the "No-Build Alternative" for the entire South Mountain Freeway to examine the effects of not building the freeway as proposed by MAG.

The Draft EIS will be made available for at least 90 days for the public to review. During that comment period, one public hearing will be held on the contents of the Draft Environmental Impact Statement.

From there, the public will have another 60-day opportunity to comment on the Final EIS. The comments received during both 90-day and 60-day comment periods will be used by ADOT and FHWA in making a final decision regarding the project. That final decision will be presented in the Record of Decision by FHWA. ADOT will begin acquiring complete the right-of-way acquisition process after the final decision is made.

As part of the final decision-making process, ADOT will work with the MAG regarding the study recommendation and the regional support to fund the project as part of the Regional Transportation Plan approved by voters. Should a build alternative be selected for the South Mountain Freeway, the Regional Transportation Plan designates the construction funding available in Phases I and II of the Regional Transportation Plan.

Introduction to the Phoenix Urban Area Regional Freeway Systme
On October 8, 1985, the voters in Maricopa County approved Proposition 300 to establish a one-half cent transportation excise tax (commonly called the one-half cent sales tax) for construction of controlled access highways. These controlled access facilities must be on the Regional Transportation Plan of the Maricopa Association of Governments (MAG) and the State Highway System. The facilities are to be constructed and maintained by the Arizona Department of Transportation. In accordance with A.R.S. 28-6538, ADOT allocates a portion of State Highway User Revenue Funds on controlled access highways in Maricopa County. Also, federal funds can be used in connection with construction of certain segments of the controlled access system. More | Close

On November 8, 1994, voters of Maricopa County defeated Proposition 400 that proposed extension of the current one-half cent transportation excise tax an additional ten years (through 2016) and imposed a new one-half cent transportation excise tax through 2016. Proceeds of the new tax would have been divided equally for freeway and public transportation purposes.

On December 13, 1994, former Governor Symington presented a plan to complete the Regional Freeway System. The plan included additional funding from higher sales tax forecasts, a greater allocation of MAG Federal funds earmarked for freeways and ADOT generated budget savings. The plan further recommended deletion of certain corridors and corridor segments, proposed higher bonding levels and included corridor scope reductions to lighting, landscaping, structure widths and freeway lanes.

On November 20, 1996, the MAG Regional Council approved a Freeway / Expressway Plan for the Lifecycle Program, FY98 - 2006, that: advanced projects, added a Grand Avenue Improvement Project, added a project to complete the I-10 / Santan / South Mountain TI, west 1/2, and added a "Set a Side" project for a South Mountain expressway in lieu of a Toll Road (privatization project).

Also on November 20, 1996, the MAG Regional Council identified funding for a Long Range Plan, FY2007 - 2015. Previously Unfunded Red Mountain, Santan, and Sky Harbor segments were prioritized, and a Grand Avenue Improvement Project was added and prioritized.

In April 1999, the State Legislature passed SB1201 which provided State Infrastructure Bank (SIB) funding to assist in financing the acceleration of the Regional Freeway Program by the end of 2007. Governor Jane Dee Hull, ADOT and MAG have prepared plans to complete the Regional Freeway System by the end of 2007 using innovative financing alternatives.

The concept of a Lifecycle Program refers to a programming approach that includes the usual five year programming period and also recognizes the need to forecast and allocate funds through the full life of major funding sources. As a result, the enclosed Regional Freeway Program covers the full period of the Proposition 300 one-half cent tax extending through fiscal year 2006. In this manner, the resources for construction of the Regional Freeway System can be fully managed both from a short and long term perspective, ensuring that the maximum benefit is returned to the taxpayer. Additionally, the ADOT Lifecycle Program reflects a fiscal balance between anticipated revenues and expenditures. Construction of the Regional Freeway Program has been scheduled on that basis. This management tool ensures that both ADOT and MAG maintain a realistic planning and construction schedule predicated upon funding, and provides periodic reports to the public and other governmental agencies.

Program Scheduling Assumptions:

  • Project delivery system improved
  • Early Completion General Plans
  • Early acquisition of Right of Way
  • Completion of Environmental Corridor Studies
  • No major design changes after 30% plans are completed
  • Support of major stakeholders (cities, county, utility companies & federal agencies)
  • Availability of Design-Build contracting

Program Financing Assumptions:

  • $200 million new State Infrastructure Bank (SIB) / Highway Expansion and Extension Loan Program (HELP)
  • $250 million of Grant Anticipation Notes (GAN)
  • Continued funding from ADOT statewide program
  • Continued ADOT and MAG federal aid funding
  • Future Vehicle License Tax initiatives will be revenue neutral
  • Interest rates are stable
  • Project costs maintained within program inflation contingency
The Lifecycle Program for the Regional Freeway System provides an effective management tool and a comprehensive view of planned construction. This philosophy will assist in maximizing transportation dollars and provide a focus on future transportation needs.

Frequently Asked Questions
People throughout the study area have posed questions to the South Mountain Corridor Team. Some questions cannot be fully answered until later in the study process. More | Close

1. What does the outcome of the Gila River Indian Community’s vote mean for the South Mountain Freeway study? Will an alignment on the Gila River Indian Community be considered?
The Gila River Indian Community’s (GRIC or Community) vote on February 7, 2012 represents an important milestone for the South Mountain Freeway Study.

At the request of the Gila River Indian Community in January 2010, the Arizona Department of Transportation (ADOT) and MAG worked together to identify a potential freeway alignment on Community land. The alignment followed a route consistent with the Community’s 1998 Gila Borderlands Regional Planning Study. When no “fatal flaws” were identified, in late 2011 the Community Council passed a resolution to hold a Community-wide referendum on the freeway. The referendum asked members whether they supported an on-Community alignment, supported an off-Community alignment, or whether they supported a “no-build” alternative.

The GRIC election on February 7, 2012 preferred the “no-build” option for construction of the Loop 202 South Mountain Freeway. This means, moving forward, an alignment of the South Mountain Freeway cannot be located on the Gila River Indian Community. The Pecos Road Alternative will be carried forward in the Draft Environmental Impact Statement (EIS), as well as the consideration of a No-Build Alternative.  The Community’s position regarding “no-build” will be considered as part of the Draft EIS.

As the process moves forward, ADOT and MAG will continue to coordinate with the Community on remaining concerns and potential methods for mitigating those concerns.

2. Has MAG made any recommendation regarding the 59th Ave alignment?
In October 2009, the Maricopa Association of Government’s (MAG) Regional Council voted to approve the revised Regional Transportation Plan (RTP). This plan includes the shift of the Western Section alignment between Lower Buckeye Road and Interstate 10 (I-10) to connect at 59th Avenue (rather than 55th Avenue).

3. Why has the 55th Avenue Alternative been moved to 59th Avenue?
Responding to budget shortfalls created by declining revenue, MAG began to study methods to reduce freeway costs. There was also public concern about the number of potential residential and business acquisitions. From this analysis – two key changes were made:

  • Reduce the proposed freeway to eight lanes from ten, which allows the needed right-of-way to be reduced;
  • Shift the alignment to connect with the I-10 at 59th Avenue.

4. What is the status of the EIS?
ADOT is currently revising the Administrative Draft Environmental Impact Statement (Draft EIS) and preparing the document for legal and cooperating agency review. Following these review processes, the Draft EIS will be prepared for public release.

5. What is the status of the "parkway" proposal?  Is it even being given due consideration???
The study team and ADOT provided MAG with a number of concepts, cost estimates, and an impact analysis for a parkway concept, either as the final configuration or as an initial phase of building a freeway. The MAG Transportation Policy Committee ultimately decided not to include a parkway concept as the recommended type of roadway for the proposed project due to the projected traffic demand and operational concerns.

6. Has a corridor along Pecos Road already been decided?
No, however the Pecos Road route was identified as a result of the 1988 state-level Environmental Assessment (EA). This alternative, along with the consequences of  not building the freeway, are currently being studied. Currently, the Pecos Road alignment is the only eastern section alternative under consideration in the Draft EIS.

7. Why is ADOT conducting a second environmental study?
Much has changed in this area since the 1988 state-level EA was completed. The Draft EIS is being prepared in light of new development in the area as well as changes in design standards and environment regulations, and to qualify for federal funds.

8. If the Pecos Road alignment is not a foregone conclusion, then why has ADOT purchased right-of-way along that alignment?
ADOT purchased some right-of-way in the corridor along Pecos Road when it was adopted as the alignment in 1988. Currently, ADOT is acquiring right-of-way to preserve the viability of the corridor and to minimize future relocation of homes and businesses as part of the agency’s long-range planning efforts. Should another alternative be adopted as a result of this study, ADOT can dispose of the land that has been acquired but is no longer needed.

9. Will the fact that ADOT already owns right-of-way in this corridor influence the final decision?
No, FHWA regulations do not allow the ownership of right-of-way to be a factor in the decision regarding the adoption of an alternative.

10. What factors will be considered in choosing an alternative?
A major factor is how well an alternative might improve future mobility, while minimizing impacts on the built and natural environment. Some factors that will be considered include air quality, cultural sites, environmental justice, threatened and endangered species, potentially hazardous materials, residential and business relocations, utilities, local land use plans, agricultural lands, traffic operations, cost, noise, historic/public park land and public and jurisdictional acceptability.

11. What about truck traffic that might be generated by a new highway?
One of the factors that will be considered in this study is the amount of truck traffic that would be generated and its potential impact on the surrounding community. The MAG regional travel demand model forecasts approximately 10 percent truck traffic on the South Mountain Freeway in 2035. The forecast truck traffic is based on existing traffic studies and projected socioeconomic data. This percentage is similar to the current conditions on I-10 between Loop 101 and I-17 and on US 60.

12. Will the public have a voice in choosing an alternative?
Yes, an extensive effort is ongoing to keep the public informed of the progress of the study and to gain public input. Issues, concerns and opportunities expressed by citizens will be considered in the ultimate decision of whether or not to build the proposed freeway, what should be built and where it should be located.

13. Will anything other than a freeway be considered?
Other non-freeway alternatives have been considered. Among other things, the study takes into account improving existing freeways, improving or expanding other travel modes, strategies to reduce travel demand, and various roadway configurations. This study will examine not only the potential impacts from improvements, but also the consequences of building nothing. As proposed by the Maricopa Association of Governments, the South Mountain Freeway would be part of the regional freeway system – a multimodal approach to improve traffic in the Valley as part of the Regional Transportation Plan. Other transportation improvements, like mass transit and local roads are specified in the Regional Transportation Plan and are considered during the evaluation of this proposed new freeway.

14. Is it possible that nothing will be built?
Yes, that is one of the options being studied. It is important to recognize that impacts can occur by doing nothing. The no-build alternative is being evaluated in the Draft EIS.

15 Would air, noise and visual quality be impacted by construction of a new road or freeway?
A major purpose of this study is to determine the potential impacts on air, noise and visual quality and to look for ways to lessen those impacts. The South Mountain Freeway is a large complex project and the study team is analyzing potential impacts.

16. How long will this study take to complete?
The study began in July 2001. Traditionally, this type of study takes five to seven years to complete. However, this will ultimately be determined by issues and impacts that are discovered during the course of the study. Based on current progress, ADOT anticipates that a final decision will be reached by the end of 2013.

17. When is something likely to be built?
If the outcome of this study is a build alternative, the timing of construction will depend upon funding availability in conjunction with final design completion, right of way acquisition, and utility relocation. As part of the current study, a document called an Implementation Plan will be produced. This document will recommend how to construct the overall project, including the length of construction segments and a sequence for those segments. The Implementation Plan might also recommend improvements to existing roadways within the study area. A South Mountain Freeway build alternative is included in the RTP; exact timelines for funding are determined annually through the Five-Year Program planning process. The current Five-Year Program includes funding for construction of the freeway in fiscal year 2014.

18. Where would the corridor join I-10 to the west of Phoenix?
ADOT has designated the 59th Avenue connection (W59) with I-10 (Papago) as the preliminary preferred alternative for the West Valley connection. This is an adjustment from an earlier decision identifying 55th Avenue (W55) as the western connection.

19. Is it likely that construction of a new road or freeway would require the acquisition of existing homes or businesses?
It is likely that the proposed South Mountain Freeway would require the acquisition of a number of existing homes and/or businesses. One purpose of this study is to determine the extent of new right-of-way that would be needed for each possible alternative. ADOT continues to work with all Valley municipalities to protect possible freeway alignments as part of a commitment to measured growth. With changes to the Regional Transportation Plan, ADOT already owns more than 90 percent of the needed right-of-way along Pecos Road, should that alternative be approved for construction.

20. Isn’t the real purpose of a South Mountain Freeway simply to act as a bypass to divert trucks from downtown Phoenix?
The primary purpose of this study is not to create a "truck bypass" for downtown Phoenix. The study is intended to assess the overall transportation needs of the entire Phoenix metropolitan area and to determine the best way to meet those needs. This proposed freeway is part of a regional system, which was developed to improve mobility in the region by increasing capacity and providing alternatives to allow traffic, including truck traffic, to bypass already congested routes. Like other “loop” freeways in Metro Phoenix, the proposed South Mountain Freeway would be a commuter corridor, helping to move local traffic between the east and west portions of the Valley. In fact, a truck bypass route already exists using I-8 and State Route (SR) 85. This route is clearly marked for trucks and is a designated routing for CANAMEX traffic. Many of the trucks you see in the metro area need to come into the city core – either to make deliveries, to access terminals, or for other commercial activities.

21. How is an Environmental Impact Statement different from the Environmental Assessment that was conducted in 1988?
The 1988 state level Environmental Assessment was prepared in order to satisfy state requirements only. In order to make any resulting project eligible for federal funding, the current study will satisfy federal requirements and will have to comply with the National Environmental Policy Act. Under this act, an Environmental Impact Statement is required for this project due to the potential of substantial impacts on the environment and surrounding communities. An Environmental Impact Statement is different from an Environmental Assessment in that it will address in detail a number of alternatives to satisfy the transportation needs in the corridor. The Draft Environmental Impact Statement is currently under review by the various government agencies involved with the project.

22. Will the current study be influenced by the 1988 Environmental Assessment?
The current study, known as an Environmental Impact Statement, will not supplement or update the 1988 state level Environmental Assessment. It is an entirely separate study and will not depend on the data collected in 1988. The 1988 Environmental Assessment was prepared in order to satisfy state requirements only. In order to make any resulting project eligible for federal funding, the current study will satisfy federal requirements and will comply with the National Environmental Policy Act.

23. The future is light rail so why would ADOT even consider building another freeway, which will only add to our congestion and air pollution problems?
The study will consider feasible alternatives, including light rail transit, travel reduction strategies, improving existing roads, and the consequences of doing nothing at all. ADOT and the Maricopa Association of Governments seek multimodal options for supporting the needs of the traveling public in the Valley. Transportation options are designated through collaborative, long-range planning processes by MAG as the regional planning authority.

24. If ADOT builds a freeway, will it be built wide enough so it doesn’t have to be torn up and rebuilt in a few years?
The South Mountain Freeway would be constructed as an eight-lane freeway (three general purpose lanes and one HOV lane in each direction). The freeway would not be designed to accommodate future widening. This change in scope will still meet the transportation needs of the Valley, but reduce costs at a time when revenues have dropped significantly. 

25. Will the Environmental Impact Statement include an analysis of the amount of diesel fumes that someone living adjacent to a freeway might be exposed to?
Potential changes in air quality are one of the key areas that will be studied in the Draft Environmental Impact Statement.

26. Once an alignment is decided, will we have a year or so to make our case?
This study, which began in July 2001, is expected to be completed by 2012. During the study process, community members will have various formal and informal opportunities to ask questions, express opinions and provide comments about the proposal. We will work to involve the public in this investigation and decision-making process throughout the study. The environmental report will have a 90-day comment period, public hearings and additional comment time for the Final EIS to incorporate layers of public input.

27. What can we do to get Pecos Road taken off the board?
The Pecos Road alignment for a South Mountain Freeway was identified in a state-level Environmental Assessment completed in 1988 and that alignment was adopted by the State Transportation Board. However, as part of the current study all reasonable alternatives are being considered. The Pecos Road alignment is considered a reasonable alternative in conjunction with a western section alternative which would meet the established purpose and need. At this time, there are no other reasonable and prudent alternatives in the eastern section.

28. If it won’t help traffic congestion (in Ahwatukee) why consider building a freeway?
When ADOT determines if a freeway should be built, the agency must consider numerous factors including local and regional transportation needs, project costs and environmental considerations. This decision has to be based on the transportation needs of the entire Phoenix metropolitan area as part of a comprehensive, regional approach to transportation solutions. Furthermore, this freeway was proposed as part of a regional plan that ADOT is charged with studying, but which is developed collaboratively by citizens and leaders from across the Valley through MAG.

29. Are other viable alternatives in Ahwatukee, other than the Pecos Road alignment, being considered?
Other alternatives were considered during the alternatives analysis phase of the study, but were eliminated from consideration due to their substantial impacts or their inability to satisfy the purpose and need of the proposed action; these alternatives were located north of Pecos Road. The only alternatives in the Ahwatukee portion of the study area that are still being considered are the Pecos Road alignment or not building the freeway.

30. Will the study include potential increases in crime that might result from having a freeway built through our community?
The Environmental Impact Statement will not include an official assessment of crime statistics. However, the City of Phoenix has provided information to the Citizens Advisory Team addressing this issue. While Phoenix Police indicated there was not specific data on a correlation between freeways and crime rates, the incidences of criminal activity seemed to be related more to the type of development adjacent to a freeway.

31. Would the potential freeway be built below existing ground?
The study team is currently in the process of analyzing the below-ground option with a smaller freeway configuration (eight lanes). The results of this analysis will be part of the Draft EIS and Location/Design Concept Report. However, it is anticipated that the change to a smaller configuration would not change the overall conclusions from the original analysis. Results of the original analysis indicated that in an effort to reduce impacts by depressing the freeway in the eastern section, ADOT would be required to spend an additional $400 million for construction and right-of-way, displace an additional 300 residences, maintain additional pump stations and detention basins for the life of the freeway, and would still have noise-related impacts requiring mitigation. Due to the fact that the below-ground option would result in substantially greater costs and residential displacements, this option was previously eliminated from further study. Freeways in the region all have above- and below-ground segments, as is proposed with this corridor.

32. Where would the interchanges be located?
Potential traffic interchange locations are being considered at approximately one-mile intervals at major street crossings. ADOT has been working with local communities and jurisdictions regarding potential locations. The following locations are currently proposed:

Western Section
Van Buren Street
Buckeye Road
Lower Buckeye Road
Broadway Road
Southern Avenue
Baseline Road
Dobbins Road
Elliot Road

Eastern Section
51st Avenue
17th Avenue
Desert Foothills Parkway
24th Street
40th Street

The locations are not final. ADOT is still in the process of coordinating with the affected jurisdictions.

33. How much influence will developers have in this process?
No more than any other citizen.

34. Will the City of Phoenix be able to influence the study?
The City of Phoenix represents the citizenry of a major portion of the study and is an active participant, as are the other municipalities and regional planning organizations in this area. As a member agency of the Maricopa Association of Governments, the City will have an opportunity to grant funding/approval should the project advance.

35. Would the high water table near the Salt River preclude construction of a depressed freeway?
The data that we are currently collecting about the study corridor will include such things as water resources and groundwater levels. This information will help us determine the types of design alternatives that would be feasible. This information will be available both in the Water Resources Technical Report as well as the EIS.

36. Would this freeway be part of the planned CANAMEX highway?
No. It is not the intent of ADOT or FHWA to include this proposed freeway as part of the CANAMEX corridor. In fact, the CANAMEX corridor in Maricopa County takes trucks from I-10 south of the Valley across I-8 to State Route 85, avoiding the metro-Phoenix area. Improvements are under way to convert this route into a higher-capacity, freeway quality route.

37. How would the existing Santan/Interstate 10 Interchange connect to the west?
The existing interchange was designed as a temporary connection with Pecos Road. It also is designed so that a permanent connection with the proposed South Mountain Freeway could be made if the freeway would be constructed on or near the Pecos Road alignment.

38. Will anything be built through South Mountain Park/Preserve?
Federal restrictions prohibit intrusion of a federal project such as this into a park, like South Mountain Park/Preserve, unless it can be shown that there is no feasible and prudent alternative to avoid such an intrusion. At this time, the study team has not identified feasible and prudent alternatives to avoid impacts on the park. As such, the freeway would go through the southern limits of the park. ADOT is working closely with park stakeholders to minimize impacts and address various concerns.

39. Can the Pecos Road corridor be changed?
Yes, the Pecos Road corridor was identified as the most appropriate alternative in 1988. However, the Environmental Impact Statement will consider a range of reasonable, present-day alternatives. However, at this time, no other alternatives have been identified. Should those options be presented for study, the team will fully evaluate.

40. What are the other alternatives?
Through the study’s public involvement efforts, over 30 alternative freeway routes were initially proposed. The study team evaluated the intent of each of these routes and developed a series of alternatives that were evaluated during an initial alternatives screening effort.

The screening of these alternatives resulted in three connection alternatives (55th Avenue, 71st Avenue and Loop 101) on the west side of the study area and one (Pecos Road/Loop 202) on the east side of the study area. In response to budget shortfalls created by declining revenue, MAG began to study methods to reduce costs. This analysis resulted in a shift of the 55th Avenue alternative to 59th Avenue. These alternatives, with variations, are being analyzed in detail in the Draft Environmental Impact Statement.

41. Will storm water runoff be controlled? Where will the water go?
If a new freeway is built, it would be designed to control storm water runoff and prevent flooding. In the western section, runoff would be discharged into the Salt River. In the Eastern Section, runoff would be discharged to the south to the Gila River Indian Community. The rate of discharge would not be greater than the existing rate of discharge.

42. Will there be access to the Gila River Indian Community from the traffic interchanges in the Eastern Section?
Federal law prohibits the denial of access to any community. The traffic interchanges would give the Gila River Indian Community access to the freeway if a roadway is constructed from the south.

43. If we can look forward to a level of service "F" in the future, what level of service do we have now?
Current level of service varies according to the time of day. We already are experiencing level of service "F" on some freeways during morning and evening rush hours. Traffic projections show, however, that this condition is likely to occur more often and last for longer periods of time in the future without improvements to the Regional Freeway System.

44. What is pass-through traffic?
Traffic that neither starts nor ends in the Valley is referred to as “pass-through.” An example is I-10 traffic that originates in Los Angeles and passes through the Phoenix area without stopping on the way to El Paso.

45. Has anyone looked at Riggs Road as a truck bypass?
During initiation of the Environmental Impact Statement process, according to protocol, ADOT approached the GRIC Natural Resources Standing Committee (NRSC) with a request to study alternatives on Community land as far south as Riggs Road, an often-suggested possible route by the public.

Nearly two-thirds of the alternative would be on Community land. While the Riggs Road Alternative would serve regional mobility needs, particularly of those living in the Maricopa area, meeting this travel demand would not address any specifically identified planning goals for an integrated regional transportation network. The Regional Transportation Plan identifies the proposed freeway as a critical link in the Regional Freeway System, both in completing it and in optimizing overall system performance as well as that of specific existing links such as Loop 202 (Santan Freeway). The Riggs Road Alternative would not complete the Loop 202 system, thereby causing substantial out-of-direction travel for motorists. The alternative would not be prudent and feasible because it would not meet the proposed action’s purpose and need and, therefore, was eliminated from further consideration.

46. Why not do what was done with the Loop 101 in Scottsdale: pay the Indian Community for the land and put it there?
ADOT continues to discuss a range of transportation-related topics with the Community. Ultimately, it is up to the Community, as a sovereign nation, to decide whether it will allow an alignment on its land. Discussions are ongoing between ADOT, MAG, FHWA and GRIC to allow the exploration of additional alternative options.

47. What kind of freeway design would be needed for the Pecos Road alignment?
Traffic studies show that a freeway, similar to the Pima Freeway or Red Mountain Freeway would be needed on the Pecos Road alignment. Potential impacts will be presented officially in the Draft EIS.

48. Have you determined how many vehicles would be likely to use the highway?
It is estimated that up to 170,000 vehicles per day will be using the South Mountain Freeway each day in 2035.

49. Will trucks carrying hazardous cargo be allowed to use the highway?
Yes, the only freeway locations in the Valley where hazardous cargo is prohibited is I-10 through the Deck Park Tunnel and on Loop 202 (Red Mountain Freeway) along the mile-long bridge above the Salt River in Tempe. Such restrictions on this freeway are not anticipated at this time.

50. What impact would a freeway along Pecos Road have on the area’s air quality?
An air quality analysis will be conducted for each of the alternative alignments. The results of the analysis will be included in the Draft Environmental Impact Statement.

51. How do you know what the air quality impact will be before the freeway is built?
Air quality impacts are determined through sophisticated computer modeling based on predictions of the amount and nature of traffic under the worst case scenarios. The Maricopa Association of Governments provides regional air quality analysis. ADOT also conducted detailed analysis of weather patterns, at the request of community members.

52. Has a decision been made on the purpose and need for a freeway?
Yes, based on projections of population growth in the Valley, increases in the number of vehicle miles traveled, and where residences and businesses will be built, it has been determined that there is a need for an I-10 to I-10 connection of some nature south of South Mountain. We are in the process of analyzing alternatives make this connection.

53. Would the proposed South Mountain Freeway handle all of the excess traffic that is anticipated in 2030?
No, there is no single freeway that can accomplish that. This proposed roadway is seen as a part of the overall system improvements and expansion that will be needed to handle our future traffic. To address future needs, the Regional Transportation Plan includes several new and expanded freeways, improvements to I-10 in the Broadway Curve and enhancements to US 60, busing expansion, and additional studies into light rail transit. All of these projects are designed to work together to better meet the Valley’s transportation needs.

54. We don’t trust your traffic projections. We think they are flawed. Who will ensure that the projections are accurate? Who will gather the data?
The traffic projections are developed by the Maricopa Association of Governments using travel demand software that is certified by Federal Highway Administration and reviewed by the Environmental Protection Agency for air quality conformity. Final acceptance of the projections will be given by ADOT and the Federal Highway Administration.

55. How has passage of the proposed extension of Maricopa County's ½ cent transportation sales tax (Proposition 400) in the November 2004 election affected the future of the proposed South Mountain Freeway?
Passage of Proposition 400 provides the primary source of funding for construction of the South Mountain Freeway.

56. Why did ADOT select the 55th Avenue alignment as the preferred western alignment and not the proposed 71st Avenue or Loop 101 alignments?
The 55th Avenue (now 59th Avenue) Alternative was identified as the Preliminary Preferred Build Alternative after comparing each of the proposed South Mountain Freeway alternatives in terms of addressing regional transportation needs, consistency with regional and long-range planning, environmental and societal impacts, traffic operational efficiencies, estimated costs and regional and public support. The Citizen’s Advisory Team recommended the W101 connection. However, the study team considered the input of all stakeholders – including regional leaders, municipalities, historical planning, and public/CAT input – to preliminarily identify the 59th Avenue alignment as the preliminary preferred western alignment to assist with needed incremental planning as the freeway study progressed. The final alignment selections will be identified in the EIS and Record of Decision.

57. Would the eastern or the western section be constructed first?
Assuming the outcome of this study is a build alternative, the construction schedule would be determined as part of the Implementation Plan. This document would be created during final design and would recommend how to construct the overall project, including the length of construction segments and a sequence for those segments. It is anticipated that the freeway construction would begin in the Western Section. Ultimately, both sections need to be built, as required under federal regulations for new highways to have independent utility and a logical termini.

58. Is this freeway going to have elevated interchanges?
It is anticipated that most of the interchanges would be elevated. However, the design of each of the interchanges has not been decided.

59. Who makes the final decision? Who has the power to make a decision?
The final decision on the freeway alignment is a cooperative effort, involving ADOT, the Federal Highway Administration, and the Maricopa Association of Governments. As a corridor that is part of a comprehensive regional plan developed by MAG, ADOT serves as the agency responsible for implementation of the plan with FHWA providing federal oversight required to access federal funds.

60. Is there a guarantee ADOT will buy the homes and businesses that lie within proposed right-of-way lines on the maps?
The right-of-way lines are based on the best information available today. The lines are identified to show the area of impacts, and are a good estimate of the area necessary to construct a freeway. Some refinement of these lines would take place during the design phase, which would identify the exact properties that would need to be acquired. With specific questions about proposed right-of-way impacts, contact the ADOT Right-of-Way Group at 602.712.7316.

61. What if I own property in an alignment?
New right-of-way maps are available. Determination of the final right-of-way would be made during the design phase and involve coordination with local and regional governments should a build alternative be selected. If you have any concerns about a specific property related to the proposed South Mountain Freeway, you can contact the ADOT Right-of-Way Group at 602.712.7316.

62. Are there more meetings the public can attend before a decision is made?
At a minimum, there will be public hearings held after the Draft Environmental Impact Statement is made available to the public during the 90-day public comment/review period. A timeframe for those hearings has not yet been established. A public information meeting was held from 6-8 p.m. on Feb. 10, 2010 at Sunridge Elementary School to provide information about the W59 Alternative.

63. How is public input used?
Public comments are a vital component in the decision-making process. The interests and needs of the public along with all other social, economic, and environmental issues and impacts must be fully analyzed and included in the Final Environmental Impact Statement. Comments made during the Draft EIS development have and will continue to be used to adjust plans, explore new questions or make changes within the scope of NEPA. Additional comment periods will be available when the Draft EIS is available for public review, and when the Final EIS is released for public review.

 


The maps below represent the revised 8-lane configuration for the proposed South Mountain Freeway, as of March 2010. The right-of-way footprint is preliminary and intended for use in identifying environmental and societal impacts. The right-of-way is neither final nor intended for land acquisition purposes. Determination of the final right-of-way would be made during the final design process and involve coordination with local and regional governments should a build alternative be selected. More | Close

Archives
The text of Proposition 400 that appeared on the Maricopa County ballots in the November 2004 election, on Page 4, the publication shows the excerpt of the ballot question. (file size: 1.89MB)

Find It!
Arizona Search State Web sites. A service of Arizona State Library, Archives and Public Records.

Work Zone Safety In Arizona
Publication by the Arizona Department of Transportation providing tips to the public when driving through roadways under construction.

Common Commuter Questions
The article below, "Mysteries of Gridlock Unlocked," by Scott Craven appeared in The Arizona Republic and asks experts some common commuter questions such as: More | Close

During rush hour, traffic often comes to a halt on the freeway even when nothing is blocking a lane. What's going on?

Why can't freeways keep up with demand?

Why aren't traffic lights better synchronized? It seems drivers catch every red light.

Speeding, tailgating, swerving from lane to lane. When people slip behind the wheel, why does civility take a back seat?

During rush hour, is it faster to take freeways or surface streets?

Mysteries of gridlock unlocked
Answers to commuters' 5 common questions

by Scott Craven, The Arizona Republic, Oct. 20, 2004

Accidents. Construction. Merging lanes.

Despite all the hype over Proposition 400, which would extend the half-cent sales tax in Maricopa County for transportation, it's these things that occupy our collective consciousness and conspire to make our daily commutes a misery. Like death and taxes, that bottleneck through Tempe (or Glendale or north Scottsdale) is a sure thing.

But what if it all suddenly made sense? Would new insight into what put the "rush" into rush hour make it bearable? Would you then be able to achieve a Zen-like state behind the wheel, forgiving those drivers who trespass against you, especially when they merged at the last possible second as if unaware the lane was ending?

Probably not. You'd still be as frustrated as commuters like Jeannette Passaretti of Peoria.

"Everybody drives like they have to be in first place," she says. "But there is no first place."

For fighting the stop-and-go traffic every weekday, you deserve answers to a few burning questions on every motorist's mind.

Here they are:

1) During rush hour, traffic often comes to a halt on the freeway even when nothing is blocking a lane. What's going on?

Physics is going on. At peak travel periods, traffic moves in waves in which a drop (a motorist slows to allow someone to change lanes) can have a ripple effect, says Mark Schlappi, systems analysis program manager for the Maricopa Association of Governments.

"When traffic gets really dense, with little room between cars, any little thing can cause a slowdown," Schlappi says. "It's a chain reaction that can slow down things a lot."

Imagine a single-lane road dense with cars in which a driver brakes for a dog. The car behind him must stop as well as the next car and so on down the line. The dog moves off the road, the first driver accelerates and the motorist behind him hesitates slightly (to allow a safe distance between the two) and accelerates as well, as does the motorist behind him and so on.

The dog is long gone and yet a mile or two down the road, drivers are slowing because of the traffic wave caused by the first driver. By the time the motorists to the rear resume speed, they have no idea what caused the slowdown.

Similar, more massive, waves occur on freeways.

Drivers who allow a comfortable space between the motorists ahead of them have a positive effect on traffic flow, says Doug Nintzel, spokesman for the Arizona Department of Transportation. Unfortunately, motorists often drive with little space between them. As soon as someone hits the brakes, everyone behind him is affected.

2) Why can't freeways keep up with demand?

There simply are too many cars and not enough land or money to handle them all, Nintzel says.

"We'll never get rid of rush hour," he says. "It's just not possible in a metropolitan area the size of Phoenix."

Freeways would have to be wider, longer and more plentiful, none of which is feasible, Schlappi says. There is a limited amount of money for construction as well as a lack of space.

"If you build freeways everywhere they are needed, people will have to be displaced," Schlappi says. "Few want that to happen. Not many people are willing to move to make room for a freeway."

Measures have been taken to smooth traffic flow as much as possible, from information signs (warning drivers of problems ahead) to metered on-ramps.

But the only way to alleviate congestion is to get people out of their cars and into buses, carpools or light rail, Nintzel says.

Tim Wolf, ADOT's assistant state engineer for transportation technology, says, "We can't build enough freeways to take care of all the traffic, but we can use technology to improve on problems."

Eventually, wireless networks installed along major freeways will beam information about road conditions up ahead, with suggested alternate routes, Wolf says. Federal and state officials are discussing the technology's standards, hoping to start installing necessary equipment within three to five years.

Wolf envisions a day when each car can send and receive data along this wireless network. A computer in the BMW up ahead can sense its driver braking and alert those cars behind it. Or a traffic light will notify waiting drivers just how many more seconds until it turns green, or if an approaching car may run the red light.

3) Why aren't traffic lights better synchronized? It seems drivers catch every red light. William Chung is always seeing red.

The 64-year-old Scottsdale resident, who drives throughout the Valley on surface streets, can't remember a time he has cruised more than a mile before hitting a stoplight.

"I get stopped at every other light," Chung says. "It's so irritating. You waste time. You waste gas."

Not true, says Jim Sparks, a Phoenix traffic engineer. Nearly every light is timed. But to explain the problem, it's important to have some background.

In the 1960s, engineers placed traffic lights at mile and half-mile intersections. Lights were on a 60-second cycle (measured green to green) and simple to synchronize. In the early 1980s, Sparks says, drivers demanded left-turn arrows at busy intersections, and signal cycles increased to 90 seconds to accommodate them. To maintain synchronization, every intersection's cycle had to increase. Drivers at red lights now had a longer wait.

Phoenix, like other Valley cities , controls its traffic lights via computer network. Lights are timed to enhance traffic flow Such timing could ease traffic flow if not for two problems, Sparks says.

The first is traffic speed. Lights in Phoenix are synchronized for 36-40 mph. Ideally, motorists at 38 mph would catch one green light after another, Sparks says. But most motorists drive 10-15 mph above that.

The second obstacle is too many cars. During peak travel periods, cycles are too short to allow all cars through. Extending the cycles would not work with lights spaced just a half-mile apart, Sparks says.

"At the vast majority of intersections, people only have to wait for one or two changes of the light to get through," Sparks says. "That's better than in most cities."

Also complicating things are freeway interchanges and traffic lights at quarter-mile intersections. Freeways require longer cycles because of consistently heavy volume. Lights at the quarter mile are impossible to synchronize and thus operate via detectors, triggered by approaching cars.

4) Speeding, tailgating, swerving from lane to lane. When people slip behind the wheel, why does civility take a back seat?

Speaking of the back seat, you need look no further to partially explain the evolution of rudeness, says Leon James, a professor of psychology at the University of Hawaii who has spent nearly 20 years analyzing driving behaviors. James, also known as Dr. Driving (http://www.drdriving.org/), refers to the back seat as "road-rage nursery."

"Children spend hours just sitting there with little to do but watch," James says. "Not only do they learn bad driving behavior, but also that it's acceptable since Mom and Dad do it."

A recent study by insurance company Liberty Mutual bears this out. The study, released in August, found that teens mirror their parents' bad driving habits, from speeding to talking on the cellphone while driving.

The media also contribute to the problem, James says, as movies and TV shows are filled with everything from car chases to irate drivers.

"We learn it is OK to be rude in certain situations," he says. "And driving is certainly one of these situations."

Lyn Warder of Phoenix says she has seen more than her share of impolite drivers. What bothers her most are drivers who commit an egregious act and then act as if it was her fault.

"It really fries me when they've done something horribly wrong, rude and inconsiderate, and they (make an obscene gesture) as if I'm the one to blame," Warder says. "It seems people repeat the bad behavior that's done to them, as if trying to get even with the next guy."

Rude behavior also can be a byproduct of the detachment drivers feel when cocooned in a metal shell, James says. While most people would not curse someone for leaving a grocery cart in the middle of the soup aisle, drivers frequently will vent their frustration with obscenities and hand gestures when stuck behind a slow-moving vehicle, James says.

That detachment also helps to explain the "It's them, not me" mentality of most motorists, James says. He says that while 35 percent admit to aggressive driving habits, those same people say that 85 percent of other drivers are too aggressive.

"As long as that gap remains, people won't feel a need to change their behavior," James says. "It will always be the other guy's fault."

5) During rush hour, is it faster to take freeways or surface streets?

It depends. For shorter distances, around eight miles or less, it might be best to stick to the streets, Nintzel says. Just getting on the freeway could delay you several minutes, based on lines at the light as well as traffic backed up from ramp metering. Taking the streets to avoid those delays could give you a head start.

For longer commutes, it's usually best to fight the crowds and squeeze onto the freeways, Nintzel says. Though you will start at a disadvantage, time will quickly be made up along a route with zero traffic lights.

"Even with the bottlenecks, the freeway is going to get you there faster over longer distances," Nintzel says. Freeway construction and expansion have relieved traffic on city streets, Nintzel says. As a result, travel times may be longer when taking surface streets, but fewer cars could mean less stress when behind the wheel.

Terms and Abbreviations
Even for transportation insiders, the terms and grab-bag of abbreviations can be dizzying. A large-scale transportation project, like the proposed South Mountain Freeway, involves terms and abbreviations from a variety of disciplines, including engineering, environmental sciences, traffic management, economics, urban planning, public involvement, hydrology and geology, construction trades and more. This guide can help. More | Close

Terms

Asphaltic concrete – A mixture of asphalt cement and high quality aggregate compacted to form a pavement.

Box culvert – A structure less than 20 feet in width, which is built under a roadway and permits drainage to pass from one side of a roadway to the other.

Cattle guard – A grate to keep domestic animals from wandering onto a highway.

Chip seal – A road preservation technique using liquid asphalt with a layer of rock "chips."

Design – Pre-construction surveys, studies, photos, drafting, etc. that provide the instructions as to how the actual construction work is to be performed.

Frontage road – A surface street paralleling a controlled access highway (such as a freeway) for the purpose of permitting access to properties facing the highway.

Grade and drain – Leveling, compacting and constructing the roadbed prior to paving.

Guardrail – A rail, usually of flexible metal, secured to uprights and erected as a barrier between or beside lanes of a highway.

Landscaping – The installation of irrigation systems, plants, grass, gravel or structures to enhance the appearance of a highway and/or reduce erosion.

Level of Service (LOS) – Level of service, as it applies to traffic, is a measurement of the severity of congestion at a given point. LOS is graded from "A" to "F," with "A" being optimum conditions and "F" being one step better than gridlock.

Material sites – Areas where road construction materials such as aggregate rock and landfill can be obtained.

National Environmental Policy Act (NEPA) – NEPA was signed into law in 1970 in response to public sentiment that federal agencies should take a lead in providing greater protection for the environment. NEPA is the basic national charter for protection of the environment. It sets policy goals and provides a means for carrying out the policy.

Obligation – The commitment of funds to a project when it is advertised for bidding.

Overlay – Putting one or more layers of asphaltic concrete over an existing pavement.

Partnering – Preparing and committing to a plan of action through the team process, which includes the proactive cooperation of all key stakeholders and identifying all issues early-on to remove obstacles to the success of team goals.

Pavement preservation – An action to maintaining the surface of the pavement to extend its useful life.

Planking – The wood or rubber matting on rail/highway crossings.

Portland Cement Concrete – A high-grade concrete used to construct pavement and structures.

Preliminary engineering – Work accomplished during the design stages of a project.

Pump station – A facility which pumps water out of depressed section of roadways.

Realignment – A construction project that changes the location of an existing roadway in order to achieve a safer or more efficient design.

Regional Area Road Fund (RARF) – Funding comes from a county authority to enact transportation excise taxes through voter approval.

Retaining wall – A wall designed to prevent the banks of a depressed roadway or the uphill slope of a mountainside roadway from sliding onto the highway, or down slope wall to support the roadway.

Roadside improvements – The installation of curbs, sidewalks, gutters or other items aimed at enhancing safety, utility, condition or appearance of a roadway.

Scour protection – Preventive action to reduce damage to roadway structures near or in riverbeds.

Seal coat – A coating applied to the surface of a road to preserve the pavement.

Shoulder – The area to the side of a roadway, which may or may not be paved or improved.

Traffic management – Installation of signals, signs or pavement markings to control traffic flow.

Turn bay – An additional lane added to a roadway to permit turning traffic to pull aside prior to turning.

Two-way left turn – A designated lane located in the center of a roadway from which left turns may be made from either direction.

Utility adjustments – Work involving the installation or relocation of lines, pipes, etc.

Acronyms and Abbreviations

AADT – Annual average daily traffic

AAR – Association of American Railroads

AASHTO – American Association of State Highway and Transportation Officials

AC – Asphaltic concrete

ACEC – Area of critical environmental concern

ACFC – Asphaltic concrete finishing course

ACHP – Advisory Council on Historic Preservation

ADA – Americans with Disabilities Act

ADOT – Arizona Department of Transportation

ADPS – Arizona Department of Public Safety

ADT – Average daily traffic

ANSI – American National Standards Institute

AREA – American Railway Engineering Association

AREMA – American Railway Engineering and Maintenance-of-Way Association

ARS – Arizona Revised Statues

ASLD – Arizona State Land Department

ASTM – American Society for Testing and Materials

ATQI – Arizona Transportation Quality Initiative

ATRC – Arizona Transportation Research Center

AVE – Arithmetic mean

BDRY – Boundary

BIA – Bureau of Indian Affairs

BLM – Bureau of Land Management of the U.S. Department of the Interior

BLVD – Boulevard

BMP – Best management practice

BNSF – Burlington Northern Santa Fe Railroad

Board – Surface Transportation Board

BOD – Biological oxygen demand

BR – Bridge

Btu – British thermal unit(s)

C – Celsius

CAA – Clean Air Act of 1970

CAAA – Clean Air Act Amendments of 1990

CANAMEX – The CANAMEX Trade Corridor was defined by Congress in the 1995
National Highway Systems Designation Act. According to federal law, the corridor in Arizona, follows I-19 from Nogales to Tucson, I-10 from Tucson to Phoenix, US 93 in the vicinity of Phoenix to the Nevada Border. ADOT and MAG have approved an I-10 to State Route 85 to US 93 route for CANAMEX traffic to avoid the metro area.

CBC – Concrete box culvert

CEQ – Council on Environmental Quality

CERCLA – Comprehensive Environmental Response, Compensation and Liability Act

CERCLIS – Comprehensive Environmental Response, Compensation, and Liability Information System

CFR – Code of Federal Regulations

CG – Cattle guard

CL – City limits

CN – Canadian National Railroad

CN/IC – Canadian National/Illinois Central (Railroads)

CO – Carbon monoxide

CO2 – Carbon dioxide

CS – Commercial standards

CTY – City

CWA – Clean Water Act

CY – Calendar year

CYN – Canyon

dB – decibel(s)

dBA – A-weighted decibel(s)

DCR – Design Concept Report

DE – District engineer

DME – District materials engineer

DOE – U.S. Department of Energy

DOI – U.S. Department of the Interior

DOT – U.S. Department of Transportation

DR – Drain

DVUR – Daily Vehicle Usage Report

EA – Environmental Assessment

EB – Eastbound

ECP – Environmental clearance process

EIC – Employee in charge (of on-track safety)

EIS – Environmental Impact Statement

EPA – U.S. Environmental Protection Agency

EPCA – Energy Policy and Conservation Act

ERS – Environmental resource score

ESA – Endangered Species Act of 1973

EX – Excavation

F – Fahrenheit

FAPG – Federal-Aid Policy Guide

FC – Finishing course

FHWA – Federal Highway Administration

FMS – Freeway Management System

FOIA – Freedom of Information Act

FR – Frontage road

FRA – Federal Railroad Administration

FWS – U.S. Fish and Wildlife Service

FY – Fiscal year (ADOT FY: July 1 - June 30)

GC – Grade

GIS – Geographic information system

GOHS – Governor's Office of Highway Safety

GPS – Global positioning system

GR – Guardrail

GRIC – Gila River Indian Community

GRIN – Gila River Indian News

HOV – High occupancy vehicle (also known as the "Diamond Lane" or "Carpool Lane" on the freeway).

hp – Horsepower

HPMS – Highway Performance Monitoring System

HSO – Health and safety officer

HSP – Health and safety plan

HURF – Highway User Revenue Fund

HWY – Highway

I – Interstate (for example: I-10)

ICC – Interstate Commerce Commission

IR – Inconsistent and responsive application

JCT – Junction

kg – Kilogram(s)

kW – Kilowatt(s)

kWh – Kilowatt-hour(s)

Ldn – Day-night equivalent sound level

Leq(h) – Hourly energy-averaged sound level

LK – Lake

LL – Lower limit (in reference to Standard Specifications for Road and Bridge Construction).

LLC – Limited Liability Corporation

LN – Line

LOS – Level of service

LT – Lighting

MAG – Maricopa Association of Governments

MGT – Management

MOA – Memorandum/memoranda of agreement

MOU – Memorandum/memoranda of understanding

MP – Milepost

mph – Mile(s) per hour

MRS – Multiple resource score

MT – Mountain

N/A – Not applicable

NAAQS – National Ambient Air Quality Standards

NBS – National Bureau of Standards

NCHRP – National Cooperative Highway Research Program

NEPA – National Environmental Policy Act of 1969

NHI – National Highway Institute

NHL – National historic landmark

NHPA – National Historic Preservation Act of 1966, as amended

NHTSA – National Highway Traffic Safety Administration

NOAA – National Oceanographic and Atmospheric Administration

NOx – Nitrogen oxide; oxides of nitrogen

NPDES – National Pollutant Discharge Elimination System

NPL – National Priorities List

NPR – No permit required

NPS – National Park Service

NRHP – National Register of Historic Places

NSPE – National Society of Professional Engineers

O3 – Ozone

O&M – Operations and maintenance

OP – Overpass

OSHA – Occupational Safety and Health Administration

PA – Project assessment

PCCP – Portland Cement, Concrete Pavement

PE – Professional engineer

PH – Phase

PL – Percentage of lot within LL (in reference to Standard Specifications for Road and Bridge Construction).

P.L. – Public law

PM – Particulate matter

PM10 – Particulate matter less than 10 microns in diameter

POR – Party of record

PPE – Personal protective equipment (for roadway worker safety)

PSD – Prevention of significant deterioration

PT – Total percentage of lot within UL and LL (in reference to Standard Specifications for Road and Bridge Construction).

PU – Percentage of lot within UL (in reference to Standard Specifications for Road and Bridge Construction).

QA – Quality assurance

QC – Quality control

RACF – Resource Access Control Facility

RARF – Regional Area Road Fund (a voter-approved excise tax primarily used for controlled access highway construction in the metropolitan areas).

RCRA – Resource Conservation and Recovery Act

RCRIS – Resource Conservation and Recovery Information System

RES – Reservation

RLS – Registered land surveyor

RMM – Railway maintenance machine

RMP – Ramp

RNG – Range

RR – Railroad

RRX – Railroad crossing

R/W – Right-of-way

SACP – Safety Assurance and Compliance Program (of the Federal Railroad Administration)

SC – Seal coat

SEA – Section of environmental analysis (of the Surface Transportation Board)

SGN – Sign(s)

SHPO – State Historic Preservation Office

S/L – Signal lights (traffic lights).

SO2 – Sulfur dioxide

SOP – Standard operating procedure

SR – State route

ST PARK – State park

Stat. – Statute

STR – Structure

SWLK – Sidewalk

T&E – Threatened and endangered species, as determined by the Endangered Species Act of 1973

TCD – Traffic control device

TCS – Traffic counting station

TEA-21 – Transportation Equity Act for the 21st Century

TI – Traffic interchange

TV – Target value (in reference to Standard Specifications for Road and Bridge
Construction).

UL – Upper limit (in reference to Standard Specifications for Road and Bridge
Construction).

UP – Underpass

U.S. – United States

U.S.C. – United States Code

USDOT – United States Department of Transportation

USGS – United States Geological Survey

USS – United States Standard

VLY – Valley

VMT – Vehicle miles traveled

WB – Westbound

Transportation Needs
Does a need still exist as it did in 1988 for a freeway in the Southwest Valley? Yes. That is the conclusion from a recent traffic analysis and from public comment received since July 2001. Although many residents have expressed concerns about the potential environmental impacts of a South Mountain Freeway on adjacent communities, most agreed that additional transportation options are needed to support current and future needs in the region. More | Close

Maricopa County 1980-2030

According to the Maricopa Association of Governments (MAG), the region's designated planning agency, the population of the Phoenix Metropolitan Area grew by 45 percent in the 1990s to 3.1 million residents. That growth is expected to continue in the coming decades. MAG's projections show that the population will double, to 6.2 million, by 2030. Much of the growth during the 1990's occurred in the Southeast and Southwest Valley, where much of the projected future growth also is expected to occur.

Travel demand and the vehicle miles driven in the Valley are expected to increase even more than the population, according to MAG projections. Even with anticipated improvements in light rail, bus service, trip reduction programs and planned expansion of existing roads implemented in connection to voter-approval of the Regional Transportation Plan in 2004, vehicle traffic is expected to exceed the capacity of the Southwest Valley streets and highways by as much as 29 percent by 2030.

How would construction of a freeway or other major transportation improvement in the South Mountain Corridor affect the problem? While construction of a single new freeway will not solve the Valley's entire traffic congestion problem, an I-10-to-I-10 connection south and west of South Mountain would have a positive impact. MAG estimates that up to 190,000 vehicles per day would use the freeway by 2030, reducing the demand on other Valley roads.

Travel Time
MAG has conducted a travel-time analysis for 2030 showing the effects with and without the proposed South Mountain Freeway.

Library

The draft technical report summaries that are distributed to the Citizens Advisory Team are available to the public. Please note that the quantitative findings and graphics are intended for discussion purposes about potential project impacts. Updated information will be presented to the public as part of publication of the Draft Environmental Impact Statement, Final Environmental Impact Statement and, if an action alternative were selected, in the final design process. Changes to the technical report summaries will be based on issues such as:

  • Refinement in design features through the design process
  • Updated aerial photography as it relates to rapid growth in the Western Section of the Study Area
  • Ongoing communications with the City of Phoenix regarding measures to minimize harm to Phoenix South Mountain Park/Preserve
  • Ongoing communications with the Gila River Indian Community (Community) regarding granting permission to study action alternatives on Community land
  • Ongoing consideration of public comments
  • Potential updates to traffic forecasts as regularly revised by the Maricopa Association of Governments
  • Potential changes regarding updated census data
  • Regularly updated cost estimates for construction, right-of-way acquisition, relocation and mitigation

Even with these factors possibly affecting findings, the study team anticipates effects would be equal among the alternatives and, consequently, impacts would be roughly comparable. This assumption would be confirmed if and when such changes were to occur.

Draft technical report summaries include:


Documents are posted as they become available in PDF format, which requires Adobe Reader to view.

Divider

On The Move Our Valley Freeway System is part of the 2004 voter-approved Regional Transportation Plan. We are working hard with our transit partners to implement the voters’ vision and are committed to quality, safety, open communication with our neighbors, and minimal inconvenience to the traveling public.