Project 'As-Read' Bid Results
015 MO 009 H638701C 015-A-(205)T MEQUITE-LITTLEFIELD-NORTH HWY (FARM RD TI)
|
Flagstaff District Item #10410
|
|
Engineering Specialist: Howard Sara Pre-Qualification: YES Bid Opening: 11/9/2012 11:00:00 AM
|
SYSTEM ENHANCEMENT-OTHER ENHANCEMENTS
|
|
|
|
The proposed project is located in Mohave County near the town of Littlefield, on I-15 near MP 9.6. The work consists of constructing a new Equipment Pass (concrete box culvert) under the freeway adjacent to the existing equipment pass. The work includes excavation, pavement markings, paving, minor drainage improvements, lighting, erosion control and other related items.
The work also includes repairs to the bridge joints on Virgin River Bridge No. 1, and placement of methacrylate sealant over the entire bridge deck.
|
|
|
| Bid Amount |
Contractor Name |
Contractor Address |
|  $3,288,043.00   |
DEPARTMENT |
PHOENIX, AZ |
|  $3,308,460.65   |
WADSWORTH BROTHERS, INC. (FN) |
DRAPER, UT |
|  $3,336,281.10   |
MEADOW VALLEY CONTRACTORS, INC. |
PHOENIX, AZ |
|  $3,390,959.46   |
VASTCO, INC. |
CHINO VALLEY, AZ |
|  $3,406,803.65   |
INTERSTATE ROCK PRODUCTS, INC. |
HURRICANE, UT |
|  $3,492,444.67   |
RALPH L WADSWORTH CONSTRUCTION COMPANY LLC |
DRAPER, UT |
|  $3,499,339.51   |
W W CLYDE & CO. |
MURRAY, UT |
|  $3,545,165.30   |
FANN CONTRACTING, INC |
PRESCOTT, AZ |
|  $3,911,580.20   |
HAYDON BUILDING CORP |
PHOENIX, AZ |
|  $3,957,462.59   |
FNF CONSTRUCTION, INC. |
TEMPE, AZ |
|  $4,333,333.00   |
LAS VEGAS PAVING CORPORATION |
LAS VEGAS, NV |

Last Updated 05/23/2013 04:05 AM
|