| Project
Summary |
Add
one general purpose lane in each direction in the existing
median. Local and state officials approved funding for
this project in December 2006 as part of the State Transportation
Acceleration Needs (STAN) funding. |
| Schedule |
RTP
Phase 1 - 2006 to 2010
STAN funding approved - December 2006
Begin final design - Summer 2007
Begin construction - Early 2009
Open to traffic - Spring 2010 |
| Current
Development Phase |
Planning
(as of February 2007) |
|
|
 |
Our Valley Freeway System is part of the 2004 voter-approved Regional Transportation Plan.
We are working hard with our transit partners to implement the voters’ vision and are committed to quality,
safety, open communication with our neighbors, and minimal inconvenience to the traveling public. |
|
|
|