Evaluation Criteria
Each project proposal will be scored according
to ADOT specific criteria. A proposal can receive a maximum
of 100 points. A summary of the criteria is described in
the table below.
The ADOT document Round
17 Evaluation Criteria contains the complete criteria
for the Round 17 cycle.
| |
Evaluation Criteria |
Points
Possible |
1 |
Overall Project Considerations / Objectives |
35 |
2 |
Project Need / One Time Opportunity |
10 |
3 |
Project Maintenance |
10 |
4 |
Cost-Effectiveness / Reasonable Cost Factors |
10 |
5 |
Community Involvement |
10 |
6 |
Community Benefit or Improvement |
25 |
|
TOTAL PROJECT SCORE |
100 |
|
|