Project Detail
|
|
160 NA 358 H811901C 160-A-(205)A TUBA CITY-FOUR CORNERS HIGHWAY (US 160) (COUNTY LINE - BLACK MESA)
|
Flagstaff District Item #14413
|
|
Engineering Specialist: Shah Manish Pre-Qualification: YES Bid Opening: 3/22/2013 11:00:00 AM
|
SYSTEM PRESERVATION-RESTORATION/REHAB/RESURFACE
|
|
|
**The proposed project is located on US 160 in Navajo County, approximately 25 miles west of Kayenta. The project begins at milepost 358.10 and extends easterly to milepost 372.50. The proposed work consists of milling the existing asphaltic concrete (AC) surface and replacing it with new AC, placing AC overlay, and placing asphalt rubber - asphaltic concrete friction course. Additional work includes reconstructing guardrail, installing guardrail end treatments, installing cattle guard, replacing pavement markings, and other miscellaneous work.
|
| Plans |
Cost |
| Bid Set |
N/A |
| Spec Set |
N/A |
| Earth Work |
N/A |
| Cross Section |
N/A |

Last Updated 05/18/2013 03:03 PM
|