US 89 - Wash, Moenkopi Wash and Five Mile Wash Bridges

US 89 - Wash, Moenkopi Wash and Five Mile Wash Bridges

Contents

This project is complete

Overview

Project Cost: $2,638,000

The Arizona Department of Transportation has initiated a rehabilitation project on several bridges along US 89 between Willow Springs and Cameron on the Navajo Nation (mileposts 471-483). Construction is expected to begin early fall and be completed in winter 2023.

The purpose of the project is to extend the service life of three bridges by rehabilitating the bridge decks, which is the riding surface that motorists drive on. Construction will take place on the following bridges: Five Mile Wash Bridge (MP 471-472), Moenkopi Wash Bridge (MP 477-478) and Wash Bridge (MP 481-482).

 

What to Expect

Work will take place from 6 a.m. to 5 p.m. Mondays through Thursdays. No work is anticipated on weekends or holidays.

US 89 will be narrowed to one lane only at the three bridges with alternating north- and southbound travel. A temporary traffic signal and onsite flaggers will direct traffic through the work zone. There will be no work taking place on the roadway between the bridges. ADOT advises drivers to plan for possible delays while the work is underway.

 

Project Area Map

US 89 - Wash, Moenkopi Wash and Five Mile Wash Bridges Map

 

Restrictions and Closures

Stay informed of traffic restrictions before they occur by subscribing to receive notifications sent directly to your email. It’s fast and easy! All we need is your email address.

For real-time information about project-related restrictions and closures, visit az511.gov or call 511, except while driving.

Remember to slow down and use caution around construction workers and equipment.

 

Traffic Alerts

...
Expect restrictions on three bridges along US 89 north of Cameron beginning Sept. 18

The Arizona Department of Transportation is advising drivers to plan for lane restrictions on US 89 between Cameron and Willow Springs beginning Monday, Sept. 18, as a new rehabilitation project gets underway on three bridges.

Drivers should expect delays when the following restrictions are in place:

  • Five Mile Wash Bridge (mileposts 471 - 472):
    • US 89 will be reduced to one lane only with alternating north- and southbound travel around the clock (24-hour restriction) beginning at 9 p.m. Sunday, Sept. 24, through Thursday afternoon, Sept. 27.
    •  On-site flaggers and a pilot car will direct drivers through the work zone while the restriction is in place.
    • A 12-foot vehicle width restriction will be in place. (Wide loads can be accommodated with advance notice).
  • Moenkopi and Wash bridges (mileposts 477 - 478 & 481 - 482):
    • US 89 will be reduced to one lane only with alternating north- and southbound travel from 6 a.m. to 4 p.m. Monday, Sept. 18, through Thursday, Sept. 21.
    • Flaggers will direct drivers through the work zone  while the restrictions are in place.

After Sept. 27, the lane restrictions will be in place at all three bridges from 6 a.m. to 5 p.m. Mondays through Thursdays through mid-October.

  • A temporary traffic signal and on-site flaggers will direct drivers through the work zone.
  • The speed limit will be reduced in the work zones.
  • No work is anticipated on Fridays, weekends or holidays.

For more information, visit the project web page.

For additional information, contact Community Relations Project Manager Jason Stephens at [email protected] or 480.751.7104.

 

Stay Informed:

...
  • By email: Subscribe to receive traffic alerts and project updates directly to your email.
  • Phone: ADOT Project Information Line: 855.712.8530
  • Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530
  • Online: Submit a question or comment through the ADOT website by visiting azdot.gov/Contact and then select “Projects” from the dropdown menu.