US 60 Centennial Wash Bridge Replacement

US 60 Centennial Wash Bridge Replacement

Contents

Overview

Project Cost: $13,707,564.30

The Arizona Department of Transportation has initiated a project to remove and replace an existing bridge on US 60 with a new seven-span bridge in the community of Wenden (milepost 62). The project limits will extend approximately one-half mile east and west of the bridge on US 60.

The new Centennial Wash Bridge will be constructed next to the existing bridge, and new paved approaches will be constructed to tie the new bridge to the existing roadway.

Project Area

Map US 60 Centennial Wash Bridge Replacement project

Project Elements

  • Removing and replacing the existing bridge with a new seven-span girder bridge.
  • Widening and paving the bridge approaches.
  • Replacing guardrails.
  • Installing new pavement markings and other related work. 

Project Schedule

Construction is scheduled to begin late spring 2024 and be completed in early 2025.
Schedules are subject to change because of weather and other unforeseen situations.

What To Expect

Work is scheduled to occur weekdays from 6 a.m. - 6 p.m., although some night and weekend work may be needed. Drivers will continue using the existing bridge while construction on the new bridge is underway. Intermittent lane restrictions will be needed for construction vehicles and equipment to access the work site.

...

Restrictions and Closures

Stay informed of traffic restrictions before they occur by subscribing to receive timely traffic alerts by email. It’s fast and easy. All we need is your email address!

For real-time information about project-related restrictions and closures, visit az511.gov or call 511, except while driving.

Remember to slow down and use caution around construction workers and equipment.

Stay Informed

...

By email: Subscribe to receive traffic alerts and project updates directly to your email.

By phone: Nicole Underwood, ADOT Community Relations Project Manager: 480.601.1575

Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530

Online: Submit a question or comment through the ADOT website by visiting azdot.gov/Contact and then select “Projects” from the dropdown menu.